Difference between revisions of "HPS 2016 Trigger Commissioning"
Jump to navigation
Jump to search
Line 2: | Line 2: | ||
Two types of runs: | Two types of runs: | ||
# ECal Pedestal Runs | # ECal Pedestal Runs | ||
− | # 20 kHz Pulser | + | |
+ | # 20 kHz Pulser | ||
+ | #* One Hour / 100 Million events at each beam current | ||
Each at 3 different beam currents: | Each at 3 different beam currents: | ||
Line 8: | Line 10: | ||
# 100 nA | # 100 nA | ||
# 200 nA | # 200 nA | ||
+ | |||
+ | The pedestal runs should be done first so that they can be |
Revision as of 18:48, 1 February 2016
Two types of runs:
- ECal Pedestal Runs
- 20 kHz Pulser
- One Hour / 100 Million events at each beam current
Each at 3 different beam currents:
- 20 nA (or lower)
- 100 nA
- 200 nA
The pedestal runs should be done first so that they can be