Difference between revisions of "HPS 2016 Trigger Commissioning"
Jump to navigation
Jump to search
Line 37: | Line 37: | ||
to update the pedestals used for the 20 kHz Pulser runs. For 25 nA, no new pedestals <br> | to update the pedestals used for the 20 kHz Pulser runs. For 25 nA, no new pedestals <br> | ||
are needed for the Pulser runs. ''Taking pedestal runs requires an ECal expert available,''<br> | are needed for the Pulser runs. ''Taking pedestal runs requires an ECal expert available,''<br> | ||
− | ''and to then update the trigger files for the subsequent Pulser runs.'' | + | ''and to then update the trigger files for the subsequent Pulser runs.'' '''If this is not the case,'''<br> |
− | + | '''all the Pulser runs can be done first with the preconfigured pedestals.''' | |
− | '''If this is not the case, all the Pulser runs can be done first with the preconfigured pedestals.''' | ||
== Phase 2: Final Tuning == | == Phase 2: Final Tuning == | ||
coming soon | coming soon |
Revision as of 19:13, 13 February 2016
Phase 0: Diagnostics
- One Run with Singles & Pairs Triggers
- trigger file: HPS/Run2016/v0.trg
- 30 minutes at any fixed current of 25 nA or greater
- This trigger configuration should give non-zero rates for all triggers:
- singles-0, singles-1, pairs-0, pairs-1
Phase 1: Preliminary Tuning
- Three Singles+Pairs Trigger Runs
- trigger file: HPS/Run2016/v0.trg
- Pair-1 is Kyle's tight A' trigger
- This trigger configuration should give non-zero rates for all triggers:
- singles-0, singles-1, pairs-0, pairs-1
- and 1 kHz pulser
- 10 minutes at each beam current:
- 25 nA (or lower)
- 100 nA
- 200 nA (If dead time is greater than 25%, lower the beam current)
- Take a snapshot of the trigger scalers at each current
- trigger file: HPS/Run2016/v0.trg
- ECal Pedestal Runs
- About 10 minutes at each beam current:
- 25 nA (or lower)
- 100 nA
- 200 nA
- About 10 minutes at each beam current:
- Three 20 kHz Pulser Runs
- trigger file: HPS/Run2016/pulser20kHz.trg
- At least 100 Million events (~1 hour) at each beam current:
- 25 nA (or lower)
- 100 nA
- 200 nA
Ideally the pedestal runs above ~50 nA should be done first so that they can be used
to update the pedestals used for the 20 kHz Pulser runs. For 25 nA, no new pedestals
are needed for the Pulser runs. Taking pedestal runs requires an ECal expert available,
and to then update the trigger files for the subsequent Pulser runs. If this is not the case,
all the Pulser runs can be done first with the preconfigured pedestals.
Phase 2: Final Tuning
coming soon