Difference between revisions of "The HPS Run Wiki"
Jump to navigation
Jump to search
Line 271: | Line 271: | ||
* [https://jira.slac.stanford.edu/browse/HPSJAVA JIRA HPSJAVA] | * [https://jira.slac.stanford.edu/browse/HPSJAVA JIRA HPSJAVA] | ||
--> | --> | ||
− | |||
− | |||
<headertabs /> | <headertabs /> |
Revision as of 15:47, 11 December 2014
[edit]
HPS Phone/Pager NumbersChecklists |
Procedures |
Manuals |
JLab Logbooks
|
RC: John Jaros
PDL: Harut AvagyanEvery Shift:
Every Run:
|
Run Plan: Dec. 8 - Dec. 10Beamline commissioning studies using the Hall B dump, followed by studies of the ECal and Trigger. The goal is to get usable CW beam to the Hall-B dump, set up the chicane, and begin to study beam backgrounds and trigger rates.
Record scaler rates, BPMs, 2H02 harp, and beam location on dump screen. Choose nominal position close to rate minimum, at old nominal, if possible.
location on dump screen. Tweak Frascati current if necessary, and record. Record scaler rates.
|
|
|
|
Webcams only accessible inside Hall gateway.
|