* If beam x/y sizes are ~<250 um, proceed with program below, otherwise ask MCC to retune | * If beam x/y sizes are ~<250 um, proceed with program below, otherwise ask MCC to retune | ||
− | * Ask MCC to deliver oval shape beam at tagger (2C24) harp: x-width ~250 um, y-width << x-width | + | * Ask MCC to deliver oval shape beam at the tagger (2C24) harp: x-width ~250 um, y-width << x-width (if tuning is going to be too long, more than 1/2 hour, use whatever asymmetric beam is available) |
− | * Continue with 2C24 (tagger) harp scans at 10 nA to check beam tilt angle motion over time, as well as beam position and width stability - ~ | + | * Continue with 2C24 (tagger) harp scans at 10 nA to check beam tilt angle motion over time, as well as beam position and width stability - ~2 hours (till about 7pm) with scans every 1/2 hour |
− | * Study beam tails as a function of current - every | + | * Study beam tails as a function of current - every 1 hours increase beam curent to 100 nA and perform tagger harp scan. <b> for harps analysis use tagger right and upstream left </b> |
{| | {| |
Revision as of 15:21, 8 March 2015
[edit]
Important Phone NumbersShift ScheduleChecklists |
Procedures |
Manuals |
JLab Logbooks
|
RC: Stepan Setpanyan
PDL: Harut AvagyanEvery Shift:
Every Run:
|
Run Plan:March 6 - 7Setup Beam to Hall-B Tagger Dump and Studies of Beam Properties.
|
|
|
|
|
|
|
|