# Aprime Runs for Trigger Diagnostics
 
# Aprime Runs for Trigger Diagnostics
 +
#* trigger file:  HPS/Run2016/v0.trg
 
#* 30 minutes at any current
 
#* 30 minutes at any current
#* trigger file:  HPS/Run2016/v0.trg
 
 
# ECal Pedestal Runs
 
# ECal Pedestal Runs
 
#* About 10 minutes at each beam current:
 
#* About 10 minutes at each beam current:

Revision as of 18:17, 4 February 2016

Phase 1

  1. Aprime Runs for Trigger Diagnostics
    • trigger file: HPS/Run2016/v0.trg
    • 30 minutes at any current
  2. ECal Pedestal Runs
    • About 10 minutes at each beam current:
      • 25 nA (or lower)
      • 100 nA
      • 200 nA
  3. 20 kHz Pulser Runs
    • trigger file: HPS/Run2016/20kHz.trg
    • At least 100 Million events (~1 hour) at each beam current:
      • 25 nA (or lower)
      • 100 nA
      • 200 nA

Ideally the pedestal runs should be done first so that they can be used
to update the pedestals used for the 20 kHz Pulser runs. This requires
an ECal expert available, and to then update the trigger files for the
subsequent Pulser runs. If this is not the case, the Pulser runs can be
done first with the preconfigured pedestals.


Phase 2

coming soon