(Created page with "<b>Attended</b>: .. and ''Igor''. * ''Eugene's'' report for a status of the KLF readeness. * ''Mikhail's'' report for the KFM status as a result of his and ''Tim's'' trip t...")
 
 
(10 intermediate revisions by the same user not shown)
Line 1: Line 1:
<b>Attended</b>: .. and ''Igor''.  
+
<b>Attended</b>: ''Moskov'', ''Eugene'', ''Hovanes'', ''Sean'', ''Mikhail'', ''Justin'', ''Jim'', and ''Igor''.  
  
* ''Eugene's'' report for a status of the KLF readeness.
+
* Discussion a Status KLF document for a readeness.
  
* ''Mikhail's'' report for the KFM status as a result of his and ''Tim's'' trip to Juelich.
+
* ''Eugene's'' said that one can expect delay in our schedule because of JLab budget and accelerater activity:
 
+
** The Spring 2024 run will continue till May 20, as planned. No reduction of this run will require a reduction of other spending.
* ''Sean's'' report for a software development and readeness for Intermediate ERR.
+
** The start of the Fall 2024 run will be delayed, at least to October 1, but probably to a later date.
 +
** The duration of the Fall 2024 - Spring 2025 run will be probably reduced. The old schedule assumed about 31 weeks of running for Hall D, which is barely enough for finishing data taking for GlueX-II. In some scenarios this may be reduced to 24 weeks. As a result GlueX-II+JEF may need to continue running into the Fall of 2025.

Latest revision as of 13:29, 24 April 2024

Attended: Moskov, Eugene, Hovanes, Sean, Mikhail, Justin, Jim, and Igor.

  • Discussion a Status KLF document for a readeness.
  • Eugene's said that one can expect delay in our schedule because of JLab budget and accelerater activity:
    • The Spring 2024 run will continue till May 20, as planned. No reduction of this run will require a reduction of other spending.
    • The start of the Fall 2024 run will be delayed, at least to October 1, but probably to a later date.
    • The duration of the Fall 2024 - Spring 2025 run will be probably reduced. The old schedule assumed about 31 weeks of running for Hall D, which is barely enough for finishing data taking for GlueX-II. In some scenarios this may be reduced to 24 weeks. As a result GlueX-II+JEF may need to continue running into the Fall of 2025.