Difference between revisions of "April 23th, 2024"
Jump to navigation
Jump to search
(4 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
* Discussion a Status KLF document for a readeness. | * Discussion a Status KLF document for a readeness. | ||
− | + | * ''Eugene's'' said that one can expect delay in our schedule because of JLab budget and accelerater activity: | |
− | * ''Eugene's'' | + | ** The Spring 2024 run will continue till May 20, as planned. No reduction of this run will require a reduction of other spending. |
− | + | ** The start of the Fall 2024 run will be delayed, at least to October 1, but probably to a later date. | |
− | * | + | ** The duration of the Fall 2024 - Spring 2025 run will be probably reduced. The old schedule assumed about 31 weeks of running for Hall D, which is barely enough for finishing data taking for GlueX-II. In some scenarios this may be reduced to 24 weeks. As a result GlueX-II+JEF may need to continue running into the Fall of 2025. |
− | |||
− | * |
Latest revision as of 13:29, 24 April 2024
Attended: Moskov, Eugene, Hovanes, Sean, Mikhail, Justin, Jim, and Igor.
- Discussion a Status KLF document for a readeness.
- Eugene's said that one can expect delay in our schedule because of JLab budget and accelerater activity:
- The Spring 2024 run will continue till May 20, as planned. No reduction of this run will require a reduction of other spending.
- The start of the Fall 2024 run will be delayed, at least to October 1, but probably to a later date.
- The duration of the Fall 2024 - Spring 2025 run will be probably reduced. The old schedule assumed about 31 weeks of running for Hall D, which is barely enough for finishing data taking for GlueX-II. In some scenarios this may be reduced to 24 weeks. As a result GlueX-II+JEF may need to continue running into the Fall of 2025.