Attended: Moskov, ..., and Igor.
- Agenda:
- 7th KLF Collab meeting is scheduled for September 19 [1].
- Our preparation for EER-I scheduled for the first week of August (Eugene).
- CPS status (Hovanes)
- KFM status (Mikhail)
- 128-ns status (Moskov)
- Engeneering work status (Eugene)
- KPT document is ready for ERR-I Conceptual design of KPT.
- KFM document is in progress.
- On June 20th, we had a Hovanes CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [6].
- Thermal analysis and thermal stress analysis in ANSYS (Tim)
- Summary of thermal analysis of the models (Hovanes)
- Photon beam and material budget (Pavel)
- Radiation environment, material budget and photon beam quality (Vitaly)
- Hovanes informed us that Patrizia is scheduled ERR-I for August 2nd. Committee is coming.