Line 7: | Line 7: | ||
**; [[media:CPS | ]] | **; [[media:CPS | ]] | ||
**; Tim: | **; Tim: | ||
− | + | - prototype of absorber - next two months | |
- finalization of shielding in terms of installation and deinstallation | - finalization of shielding in terms of installation and deinstallation | ||
- magnet and absorber design is nearly finalized (99% ready) | - magnet and absorber design is nearly finalized (99% ready) | ||
- reduced dose allow to operate with cheap resin | - reduced dose allow to operate with cheap resin | ||
− | ** | + | **; Pavel: |
- updated model of CPS. Main motivation to accommodate technical requirements, like all joints outside shielding | - updated model of CPS. Main motivation to accommodate technical requirements, like all joints outside shielding | ||
- new model reduces dose on magnet coils. | - new model reduces dose on magnet coils. | ||
Line 18: | Line 18: | ||
**; [[media:KLONG_2026instl_No_MRI.pdf | KLONG Installation Schedule 2026 with no MRI Magnet]] | **; [[media:KLONG_2026instl_No_MRI.pdf | KLONG Installation Schedule 2026 with no MRI Magnet]] | ||
**; [[media:KLONG_2025instl_MRI_v2.pdf | KLONG Installation Schedule 2025 with MRI Magnet]] | **; [[media:KLONG_2025instl_MRI_v2.pdf | KLONG Installation Schedule 2025 with MRI Magnet]] | ||
+ | |||
+ | - 2025 is feasible, but would require additional manpower to parallelize operations | ||
+ | - 2026 is rather relaxed. | ||
+ | - budget profile is on the way | ||
+ | - Answer to a question from Igor: an early pre-installation of CPS is not possible due to conflict in location with existing equipment. | ||
*; Space at the lab (Tim, Eugene) | *; Space at the lab (Tim, Eugene) |
Revision as of 12:29, 29 May 2024
Agenda
- Announcements
- Progress of CPS design (Tim, Pavel)
- prototype of absorber - next two months - finalization of shielding in terms of installation and deinstallation - magnet and absorber design is nearly finalized (99% ready) - reduced dose allow to operate with cheap resin
- Pavel
- updated model of CPS. Main motivation to accommodate technical requirements, like all joints outside shielding - new model reduces dose on magnet coils.
- New design, construction, and installation schedule estimates (Tim)
- 2025 is feasible, but would require additional manpower to parallelize operations - 2026 is rather relaxed. - budget profile is on the way - Answer to a question from Igor: an early pre-installation of CPS is not possible due to conflict in location with existing equipment.
- Space at the lab (Tim, Eugene)
- Need 700 sq ft general indoor storage on or off site
- 200 sq ft in ESB (KFM detector check out)
- Additional 150 sq ft in lead shed
- Assume MRI magnet comes directly to hall when available
- Recommendation #4 from ERR-1 (Moskov)
- Results of the studies
- Statement regarding the studies of KLF compatibility with MOLLER.
- On May 24, Moskov reported that accelerator folks did not have a time to check a situation with Moeller vs KLF in May and will do that in November.
- Recommendation #5 from ERR-1 (Tim)
- Results of the studies
- Statement regarding thermal cycling of the targets receiving >1 KW power.
- Any other business.
- On the next meeting, Ilya will report the KL rate from Be-target extracted from SRC measurements.
- Mikhail reported that KFM parts are moving from Juelich to JLab and will be ready for installation.
Minutes
Present: Mikhail, Tim, Edy, Pavel, Eugene, Marshall, Hovanes, Eduard, Vitaly, Beni, P.D., Igor