April 23th, 2024
Jump to navigation
Jump to search
Attended: Moskov, Eugene, Hovanes, Sean, Mikhail, Justin, Jim, and Igor.
- Discussion a Status KLF document for a readeness.
- Eugene's said that one can expect delay in our schedule because of JLab budget and accelerater activity.
- The Spring 2024 run will continue till May 20, as planned. No reduction of this run will require a reduction of other spending.
- The start of the Fall 2024 run will be delayed, at least to October 1, but probably to a later date.
- The duration of the Fall 2024 - Spring 2025 run will be probably reduced. The old schedule assumed about 31 weeks of running for Hall D, which is barely enough for finishing data taking for GlueX-II. In some scenarios this may be reduced to 24 weeks. As a result GlueX-II+JEF may need to continue running into the Fall of 2025.