KLF beamline meeting - September 6, 2024
Jump to navigation
Jump to search
Agenda
- Announcements
- Preliminary IERR Report (Hovanes)
-
- Recommendations related to the beamline group (Hovanes)
- Input for IERR simulations (trigger & tracking) (Igor)
- Beamline simulations in GEANT4 (Richard)
- Updates on FLUKA simulations (Pavel)
- Engineering design progress (Tim)
- Any other business
-
- Hall D model for RadCon (Igor)
Minutes
Present:
Igor, Eugene, Hovanes, Moskov, Vitaly, Tim, Beni, Sean, Sashi, Pavel, Richard
- There was an Intermediate Readiness Review last week for KLF during which physics analysis related topics were addressed. Members of KLF presented 12 talks to respond to the items listed in the charge of the review committee. We already received 12 recommendations that will need to be addressed by the next readiness review (ERR-2). The full report with the recommendations as well as the findings and comments will be released in a couple of weeks.
- Hovanes announced that procurements for KPT have been temporarily suspended until all concerns are addressed and the engineering designe is modified if needed. Eugene pointed out that due to the budget cuts that the procurements at Jefferson Lab are currently limited to the items that are absolutely needed for near term operations. Procurement requests of items over $250 will need justified by the requester and then approved from Physics Division.