Difference between revisions of "April 23th, 2024"

From kl project
Jump to navigation Jump to search
 
(8 intermediate revisions by the same user not shown)
Line 1: Line 1:
<b>Attended</b>: .. and ''Igor''.  
+
<b>Attended</b>: ''Moskov'', ''Eugene'', ''Hovanes'', ''Sean'', ''Mikhail'', ''Justin'', ''Jim'', and ''Igor''.  
  
* ''Eugene's'' report for a status of the KLF readiness and tentative schedule.
+
* Discussion a Status KLF document for a readeness.
  
* ''Sean's'' report for a software development and readiness for Intermediate ERR.
+
* ''Eugene's'' said that one can expect delay in our schedule because of JLab budget and accelerater activity:
 
+
** The Spring 2024 run will continue till May 20, as planned. No reduction of this run will require a reduction of other spending.
* ''Hovanes's'' report for a beamline development and readiness for ERR-II.
+
** The start of the Fall 2024 run will be delayed, at least to October 1, but probably to a later date.
 
+
** The duration of the Fall 2024 - Spring 2025 run will be probably reduced. The old schedule assumed about 31 weeks of running for Hall D, which is barely enough for finishing data taking for GlueX-II. In some scenarios this may be reduced to 24 weeks. As a result GlueX-II+JEF may need to continue running into the Fall of 2025.
* Discussion for a Status KLF document.
 

Latest revision as of 14:29, 24 April 2024

Attended: Moskov, Eugene, Hovanes, Sean, Mikhail, Justin, Jim, and Igor.

  • Discussion a Status KLF document for a readeness.
  • Eugene's said that one can expect delay in our schedule because of JLab budget and accelerater activity:
    • The Spring 2024 run will continue till May 20, as planned. No reduction of this run will require a reduction of other spending.
    • The start of the Fall 2024 run will be delayed, at least to October 1, but probably to a later date.
    • The duration of the Fall 2024 - Spring 2025 run will be probably reduced. The old schedule assumed about 31 weeks of running for Hall D, which is barely enough for finishing data taking for GlueX-II. In some scenarios this may be reduced to 24 weeks. As a result GlueX-II+JEF may need to continue running into the Fall of 2025.