X17/PRad II ERR

From Pcrewiki
Jump to navigationJump to search

UDER CONSTRUCTION...

The review will take place May 9, 2025

Review committe

Charge to the review

Here is the charge given to the PRad Collaboration for the PRad-II and Hidden Sector Search (X17) Experiments as written by Dr. Patrizia Rossi.

ERR Report

Agenda (draft)

  • 0:0 Executive Session
  • 0:0 General overview of experiments (20 min) Ashot
  • 0:0 Overview of the experimental setup, required beam parameters (15 minutes) Ashot/Dipangkar
  • 0:0 Run plan including commissioning (20 min) Ashot/Dipangkar
  • 0:0 HyCal (20 min) Ashot
  • 0:0 PRad Target (20 min) - Xiangdong
  • 0:0 GEM (20 min) - Nilanga
  • 0:0 DAQ, on-line and off-line software, trigger, slow controls (25 min) - Chao
  • 0:0 Experiment configuration layout, pre-installation, and installation schedule (20 min) Bob
  • 0:0 Radiation dose on the calorimeter (15 min) Weizhi
  • 0:0 Run documentation COO, ESAD, RSAD, etc.] (10 min) Eugene
  • 0:0 Staffing of the experiment (shifts, Run coordinators) (15 min) Dipangar
  • 0:0 Path to first publications (10 min) Haiyan
  • 0:0 Executive Session
  • 0:0 Closeout

Materials for ERR

Presentations

Documentation

Standard Run documentation

  • Conduct of Operations (COO) (Eugene)
  • Experiment Safety Assessment Document (ESAD) (Eugene)
  • Radiation Safety Assessment Document (RSAD) (Eugene, Weizhi)
  • Hall B Emergency Response Guidelines (ERG) (Eugene)
  • Pre-run checkout (Rafo, Eugene)

Operational procedures for non-standard equipment

PRad Target

  • PRad Target ePAS (Xiangdong)
  • PRad Target Operation procedures (Xiangdong)

HyCal

  • HyCal ePAS (Eugene)
  • HyCal Operation procedures (Ashot,Eugene))
  • HyCal Transporter ePAS (Eugene, Krister)
  • HyCal Transporter Operation procedures (Eugene, Krister)

GEM

  • GEM ePAS (Florian)
  • GEM Operation procedures (Nilanga, Florian)

Vacuum Chamber

  • Vacuum Chamber ePAS (Bob)