  Previous two weeks (Oct 26-Nov 9)
    - OPS: BTeam/Model meeting, operations training and engagement
    - OPS: ATLis reviews, Hall D optics ATLis, optician schedules
    - LERF: Fall two week restart/operations run (observer for a few shifts)
    - ER@CEBAF: biweekly meeting org, coordination telecons with Francois Meot
    - ODU/MEIC: Continue bunch-splitting simulations, education with Randy
    - MEIC: Simple coding simulation development for exploring gear changing
    - JACoW: Team Meeting (Nov 13-22) talk preparation
  Next two weeks (Nov 9-23)
    - JACoW: Team Meeting (Nov 13-22, Padova Italy)
    - CEBAF: AutoQuad commissioning, optics matching configuration
    - OPS: BTeam/Model meetings
    - ADMIN: Interviews (Staff I, position 11639)
    - ADMIN: Employee annual review processing

Alex Bogacz

  Previous two weeks (Oct 26-Nov 9)
    - ER@CEBAF: CEBAF ER chicane option
    - ADMIN: Tech Transfer Committee: Invention Disclosure Reviews
    - ADMIN: SBIR/STTR reviews
    - CEBAF: Restart meetings
  Next two weeks (Nov 9-23)
    - CEBAF: Startup, optics
    - ADMIN: editing JINST chapter on 'Fundamental Aspects of Muon Decay Rings'
    - ER@CEBAF: CEBAF ER transverse optics, matching to the arcs
    - ADMIN: Review  a PRST-AB paper

Dave Douglas

  Previous two weeks (Oct 26-Nov 9)
    - LERF: Fall two week restart/operations run (organization, documentation)
  Next two weeks (Nov 9-23)
    - LERF: Fall two week restart/operations run (organization, documentation),
      beam reanimation
    - LERF: energy recovery analysis for DarkLight - accommodating beam
      scattering in target (needs matching/coupling compensation as
      described above)
    - LERF: diagnostics/corrections package & operations procedures for
      DarkLight
    - LERF: Isotope kibitzing
    - MEIC: Cooler ERL design: need spec for longitudinal phase space,
      need to determine why "real" beam comes apart

Chris Tennant

  Previous two weeks (Oct 26-Nov 9)
    - LERF: operations
    - ASML: mostly completed various aperture studies for lattice
      3.0.0, still investigating some "mysteries" in results,
      computing uBI gain in compressor arcs
    - MEIC: investigating different mysteries (i.e. understanding
      behavior of transporting a magnetized beam in TStep/PARMELA)
  Next two weeks (Nov 9-23)
    - LERF: operations
    - ASML: repeat aperture study analysis for lattice 2.1 (if
      lattice becomes available and time is available)

Randy Gamage

  Previous two weeks (Oct 26-Nov 9)
    - MEIC: Longitudinal model development, elegant/esme comparisons,
      bunch merge/split parameterization
  Next two weeks (Nov 9-23)
    - MEIC: Longitudinal model development, continue bunch merge/split
      parameterization and optimization scans