2015-08-21 Accelerator Physics Biweekly Report
Jump to navigation
Jump to search
CASA Accelerator Physics
Biweekly Report: 08/08/15 - 08/21/15
Sbmitted by: Todd Satogata
Todd Satogata
-
Previous two weeks (Aug 10-21)
- CEBAF: Hall D FFB evaluation; BPM data analysis (w/Alexandre Deur); BTeam; fopt optics tuning development (w/Eric Thompson)
- ER@CEBAF: biweekly meeting; BBU model development (w/Yue Hao); trip planning
- ADMIN: IPAC'15 proceedings finalization; COOL'15 program work
- MEIC: Gear-changing summary report contribution; beam-beam model development
- ODU/MEIC: Continue bunch-splitting simulations, education with Randy
- ODU: NNSA funding proposal development (biweekly telecon)
- VACATION: 8/10(pm), 8/12, 8/14(am)
-
Next two weeks (Aug 24-Sep 4)
- CEBAF: ORFP editing; BTeam; fopt optics tuning development (w/Eric Thompson); Hall D weekly meeting
- ER@CEBAF: biweekly meeting; BBU model development (w/Yue Hao); trip planning (BNL Sep 4-11)
- ADMIN: JACoW documentation development (Board of Directors)
- MEIC: Continue beam-beam model development
- ODU/MEIC: Continue bunch-splitting simulations, education with Randy
- ODU: NNSA funding proposal development (biweekly telecon)
- FMLA: 08/28
Alex Bogacz
-
Previous two weeks (Aug 10-21)
- NuFact15 (Aug 10-15)
- Vacation (Aug 16-21)
-
Next two weeks (Aug 24-Sep 4)
- CEBAF: Check M56=0 lattices from Yves for fall run
- ER@CEBAF: continue optics longitudinal match, extraction considerations
Dave Douglas
-
Previous two weeks (Aug 10-21)
- MEIC: Wrote up magnetized beam matching note; arc to Chris for space charge simulations; DIMAD model developed to work out dechirp.
- Project E: Thinking about compressors in new optics, kibitzing to ASML
- ER@CEBAF: Meetings
- Other: DOE FWP review for LK Len
-
Next two weeks (Aug 24-Sep 4)
- MEIC: Deliver magnetized beam matching note; finish DIMAD model for dechirp; start writing technote on magnetized arc transport design.
- LERF: Clean up DIMAD deck for IR region (remove W55 wiggler and THz chicane); start reconfiguring optis to integrate detector/isotope production.
- Project E: Possibly start developing diagnostics lines pending guidance; trip planning for September.
- ER@CEBAF: Meetings, start writing on motivation section
- Other: PRL Review
Chris Tennant
-
Previous two weeks (Aug 10-21)
- MEIC: magnetized beam transport/matching, including adaption to Tstep and incorporation of Douglas optics for space charge simulation
- LERF: Continue FEL lattice to CED/LED with Michele Joyce/Theo
- Bubble Chamber: 5D line to elegant, configured zigzag harp scans for 5 MeV region, shifts awaiting measurement opportunities.
- ER@CEBAF: Meetings, measurements planning
-
Next two weeks (Aug 24-Sep 4)
- MEIC: Continued magnetized beam transport, start technote documentation
- LERF: Check FEL lattice in LED
- Project E: start evaluating momentum aperture of lattice, Touschek impact, compare to Rui's predictions
- Bubble Chamber: run planning for September, guidance for tuning (e.g. small spot size on radiator)
Alex Castilla
-
Previous two weeks (Aug 10-21)
- Dissertation writing
- Continue preparations for MEPAS teaching in Nov
-
Next two weeks (Aug 24-Sep 4)
- Dissertation writing
- Start preparations for MEPAS teaching in Nov
Randy Gamage
-
Previous two weeks (Aug 10-21)
- MEIC: Longitudinal model development
-
Next two weeks (Aug 24-Sep 4)
- MEIC: Longitudinal model development