New action items
200kV Gun
- Electrode submitted to shop
- Shop finished bushing holder, in TL-1137
- Jay can help w/ 3D electrostatic model
Gun2 NEG Tube
- Danny updated NEG tube
- John/Joe will decide on antenna plan next week
Gun3 Removal
- Matt check with Willeke next week during JLEIC meeting Gun3
- Maybe week May 8? to remove/replace Gun3 ATLIS task
Eliminating Gun Switch Software
- Kyle building a new screen, tracking to be ready in May or June