August 31, 2020 - AIPINJ Phase 1 Planning Meeting
Jump to navigation
Jump to search
Phase 1 of the injector upgrade begins in a little more than 3 weeks. The layout is final, the design work is ramping down. Daily jobs involve fabrication, assembly and testing. Integration with out groups and the SAD calendar is ramping up.
- Blue jeans link : https://bluejeans.com/909497334
We'll do the following...
- (20 min) Overview of beam line media:200821_Songsheet.pdf
- (20 min) Status of elements media:200827_AIPINJ_layout_rev5.xlsx
- (20 min) Discussion of draft schedule media:200826_AIPINJ_Schedule.xlsx