Let's meet and discuss progress of upgrade on Wednesday, July 13 @ 10am in TL-1227.

4-laser-olympics.png

Laser Installation

  • Laser table rebuild 160713 4layout.png
  • Communications to IPG/PPLN
  • Remaining tasks
  • PGun Ops Screengrab 160713 4laser.jpeg

Hardware Controls

  • Macropulse chassis installation
  • SCAM board, firmware, ioc software
  • HCO

PSS

Software Controls

  • Add 4th laser to applications
  • Add 4th laser to screens

Commissioning