September 30, 2015 - Fall Startup and Injector Tests
Jump to navigation
Jump to search
Wednesday September 30 @ 2pm in Bldg. 87 Rm. 101
Arne's priorities: Nov. 9th the following things MUST be accomplished.
- CW beam to the inline dump 85uA from A laser, 1uA from the D laser
- Wien setup for alignment of polarization to Hall-A on 5-pass
- Quads, solenoids centered (where appropriate) and the determined BPMs SOF loaded, see item 6
- Beam matched in the inj. chicane, ready for transport into the NL.
- All lasers should produce beam with the same TWISS/emittance values as measured in the inj. chicane
- RF calibration tool fully developed (anticipate Nov. 2-7 DAYS)
- quad centering tool fully developed (anticipate Nov. 2-7 DAYS)
Injector Tests and Calendar media:150929_InjectorTestList.xlsx media:150929_InjectorTestList.pdf