UITF pre-run0 commissioning steps (1/23/2020):
Hot checkout with beam and admin steps associated with commissioning plan
- Finish sending 200 keV beam to both waist height dumps, identify all the components that don’t work and get them fixed
- Call RadCon and SSG and coordinate shielding and BLM calibration (step 6 of commissioning plan)
Buncher Commissioning
- Beam to 200 keV spectrometer, find the two zero crossing phases, find crest and calibrate energy gain versus buncher gradient
- Beam to MeV spectrometer, verify zero crossing (is this step of any real value?)
- Measure bunchlength with Brock cavity, versus buncher gradient, find minimum and then scale graient to set minimum at two-cell
Optic studies
- Harp scans, measure spot sizes and compare to Elegant predictions
- Measure beam emittance
- Dipole calibration? We know it’s 200 keV beam
- Measure energy spread
Yao cavity time of flight system
- Work with Rama to see if it works
Chopper commissioning