Wednesday February 18, 2015
Jump to navigation
Jump to search
We will meet in TL 2221 on Wednesday February 18 at 3:30 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
1- Bubble Chamber progress at Argonne
Notes from this meeting:
- Bubble Chamber:
- Chamber is filled with mercury but there is a little leak.
- Tasks:
- Bubble Chamber beamline commissioning (February - May)
- Review of equipment - Bubble Chamber (May)
- Bubble Chamber at JLab (June)
- Review of operational procedures for this equipment (June)
- Accelerator 2015 Schedule:
- Spring 2015 Beam 10.5 GeV commissioning: February 13 - May 04
- SRF helium process of North Linac (NL-CHL2): May 19 - July 12
- Utilities Infrastructure Modernization (UIM) power outage: July 12 - August 10
- SRF helium process of South Linac (SL-CHL1): August 10 - September 12
- CHL2 Commissioning with new Heat Exchanger: September 01 - September 30
- Cryo/RF Restoration: September 28 - October 26
- Fall 2015 Beam 12.0 GeV commissioning: October 26 - December 21
- Bubble Chamber 2015 Schedule:
- Install in JLab Injector (June)
- Bubble Chamber tests - No beam (July)
- Commissioning with beam (August - September)