Difference between revisions of "GTS meeting 11 15 16"
Jump to navigation
Jump to search
(3 intermediate revisions by 2 users not shown) | |||
Line 5: | Line 5: | ||
− | * Laser power needed | + | * Laser power needed to generate each beam current (at 532 nm and with QE=1%): |
: [[file:BunchLaser.gif]] | : [[file:BunchLaser.gif]] | ||
+ | |||
+ | * The gun bake is complete (less than 10% in pressure over 24 hours) | ||
+ | ** We wil activate the NEGs, followed by cool down Wednesday morning | ||
+ | ** Thursday we will clean up and setup for high voltage ops | ||
+ | ** Target day for starting HV conditioning is this Friday Nov 18 | ||
+ | |||
+ | * GTS PSS certification complete, except for the laser part | ||
+ | |||
+ | * The slits are being assembled in TL1137 clean room, but there seems to be material only for horizontal slits. | ||
+ | *[[Media:haysg_JL0035130-EMS SLIT SYSTEM ASSEMBLY.pdf]] | ||
+ | *[[File:Horizontal.jpg]] |
Latest revision as of 13:45, 15 November 2016
- Bunch charge versus frequency for different average beam currents:
- Laser power needed to generate each beam current (at 532 nm and with QE=1%):
- The gun bake is complete (less than 10% in pressure over 24 hours)
- We wil activate the NEGs, followed by cool down Wednesday morning
- Thursday we will clean up and setup for high voltage ops
- Target day for starting HV conditioning is this Friday Nov 18
- GTS PSS certification complete, except for the laser part
- The slits are being assembled in TL1137 clean room, but there seems to be material only for horizontal slits.
- Media:haysg_JL0035130-EMS SLIT SYSTEM ASSEMBLY.pdf