Difference between revisions of "GTS meeting 9 11 17"

From Ciswikidb
Jump to navigation Jump to search
 
(4 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
* High current runs
 
* High current runs
 +
 +
 +
* Sajini - Differential Orbits study:
 +
:: [[media:Sajini_different_orbits-corrector_settings_11Sept2017.pdf]]
 +
:: [[media:Sajini_different_orbits-corrector_settings_11Sept2017.xlsx]]
  
  
Line 9: Line 14:
 
# Replace leaky vent valve
 
# Replace leaky vent valve
 
# Replace bad ion pump
 
# Replace bad ion pump
 +
# Activate new photocathode (new puck): 5 mm active area at center or full active area?
  
  
 
* Next Shutdown – December 2017:
 
* Next Shutdown – December 2017:
 
# Install TE011 cavity
 
# Install TE011 cavity

Latest revision as of 09:42, 11 September 2017

  • High current runs


  • Sajini - Differential Orbits study:
media:Sajini_different_orbits-corrector_settings_11Sept2017.pdf
media:Sajini_different_orbits-corrector_settings_11Sept2017.xlsx


  • Shutdown Plan:
  1. Install new YAG screen at viewer 3
  2. Fix existing harp and install 20 µm tungsten wire
  3. Add a new CEBAF-style harp with 10 µm tungsten wire (i.e, GTS will have two harps)
  4. Replace leaky vent valve
  5. Replace bad ion pump
  6. Activate new photocathode (new puck): 5 mm active area at center or full active area?


  • Next Shutdown – December 2017:
  1. Install TE011 cavity