− | === | + | ===Last Week-ish=== |
:'''Bubble Run''' | :'''Bubble Run''' | ||
::Added new harp w/ temporary controls | ::Added new harp w/ temporary controls | ||
Line 6: | Line 6: | ||
::Added x-ray card to locate beam position | ::Added x-ray card to locate beam position | ||
:'''Upgrade Preparations''' | :'''Upgrade Preparations''' | ||
− | ::Tested HVPS to 300kV in SF6 tank at 15psi | + | ::[https://logbooks.jlab.org/entry/3574117 Tested HVPS to 300kV in SF6 tank] at 15psi |
::Suitcase added to Tee, bake ~48 hours up to 165C, Tee vacuum good <100's nA | ::Suitcase added to Tee, bake ~48 hours up to 165C, Tee vacuum good <100's nA | ||
::DecaRad installation below outrigger laser table started, heads/cables ready to dress | ::DecaRad installation below outrigger laser table started, heads/cables ready to dress | ||
− | ===Next Week and Beyond=== | + | ===Today, Next Week and Beyond=== |
:Bubble will continue to run until next Friday @ 8am | :Bubble will continue to run until next Friday @ 8am | ||
:S&A begin 200kV electrode measurements 5/11 (per last week's plan) | :S&A begin 200kV electrode measurements 5/11 (per last week's plan) | ||
:Met w/ Jerry to review PSS integration plans [[media:SAD18_PSS_180511.xlsx]] | :Met w/ Jerry to review PSS integration plans [[media:SAD18_PSS_180511.xlsx]] | ||
::PSS dipole measurements vs. expected gun voltage | ::PSS dipole measurements vs. expected gun voltage | ||
− | :Upgrade Week 1 [[media:SAD_180510.docx]] | + | :Upgrade Week #1 (May 21-25) [[media:SAD_180510.docx]] |
Latest revision as of 10:51, 11 May 2018
Last Week-ish
- Bubble Run
- Added new harp w/ temporary controls
- Added ceramic break to radiator (shield aimed downstream), in series w/ FCUP
- Added Gumby (10 sec) laser shutter, tested w/ beam and remote enable/disable
- Added x-ray card to locate beam position
- Upgrade Preparations
- Tested HVPS to 300kV in SF6 tank at 15psi
- Suitcase added to Tee, bake ~48 hours up to 165C, Tee vacuum good <100's nA
- DecaRad installation below outrigger laser table started, heads/cables ready to dress
Today, Next Week and Beyond
- Bubble will continue to run until next Friday @ 8am
- S&A begin 200kV electrode measurements 5/11 (per last week's plan)
- Met w/ Jerry to review PSS integration plans media:SAD18_PSS_180511.xlsx
- PSS dipole measurements vs. expected gun voltage
- Upgrade Week #1 (May 21-25) media:SAD_180510.docx