# Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company) | # Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company) | ||
− | # Suggest we | + | # Suggest we use the Vacuum Group to build the MeV beamline (my group can help) |
# Cryo: install the helium return line, or be content to vent the helium to the test lab | # Cryo: install the helium return line, or be content to vent the helium to the test lab | ||
# SRF, need a point of contact for all things related to QCM operation, it's still confusing to me who to talk to | # SRF, need a point of contact for all things related to QCM operation, it's still confusing to me who to talk to | ||
Line 14: | Line 14: | ||
# Magnet group: give us a third trim card rack | # Magnet group: give us a third trim card rack | ||
# RF group: klystrons, high power amplifier, solid state amp, water skids | # RF group: klystrons, high power amplifier, solid state amp, water skids | ||
+ | # SSG to incorporate high power RF interlocks into PSS, recertify | ||
# Vashek: finish specifying the shielding requirements, then we start moving lead | # Vashek: finish specifying the shielding requirements, then we start moving lead | ||
+ | # RCG to install all CARMs and electronics | ||
# R&D related to low current BPMs, suggest Andy take this on, with help from Engineering | # R&D related to low current BPMs, suggest Andy take this on, with help from Engineering | ||
# Operations Group should augment Joe's modeling, using a particle tracking code | # Operations Group should augment Joe's modeling, using a particle tracking code |
Latest revision as of 09:52, 22 June 2018
Tasks before running beam to HDIce for target commissioning
- Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)
- Suggest we use the Vacuum Group to build the MeV beamline (my group can help)
- Cryo: install the helium return line, or be content to vent the helium to the test lab
- SRF, need a point of contact for all things related to QCM operation, it's still confusing to me who to talk to
- Electrical engineering: design and build the PSS BCM, our "credited control" to limit beam current/loss and prevent accidental exposure to xrays
- Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)
- Magnet group: give us a third trim card rack
- RF group: klystrons, high power amplifier, solid state amp, water skids
- SSG to incorporate high power RF interlocks into PSS, recertify
- Vashek: finish specifying the shielding requirements, then we start moving lead
- RCG to install all CARMs and electronics
- R&D related to low current BPMs, suggest Andy take this on, with help from Engineering
- Operations Group should augment Joe's modeling, using a particle tracking code
- Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review, lots of documents, lots of reviews
- Gun group needs to build a new photogun
- Need to operate the UITF on a daily basis.....
- Need access to liquid helium for weeks long periods of time (i.e., competition with LCLS)