;CEBAF
 
;CEBAF
 
:Now (+3 wks) - Run A & B
 
:Now (+3 wks) - Run A & B
:Sep 9 (+4 wks) - Gun work + 200kV beam
+
:Sep 9 (+4 wks) - HV chamber + 200kV beam
:Oct 7 (+2 wks) - PSS cert + Laser work + Docking chamber
+
:Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber
 
:Oct 22 (+3 wks) - HCO
 
:Oct 22 (+3 wks) - HCO
 
:Nov 11 (+2 wks) - Restore CEBAF
 
:Nov 11 (+2 wks) - Restore CEBAF

Revision as of 07:55, 16 August 2019

We'll meet Friday 8/16 in TL-2236 @ 9:30am

CEBAF
Now (+3 wks) - Run A & B
Sep 9 (+4 wks) - HV chamber + 200kV beam
Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber
Oct 22 (+3 wks) - HCO
Nov 11 (+2 wks) - Restore CEBAF
Nov 25 (+4 wks) Physics @ 2.2 GeV/pass
A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips
B 100nA @ 250 MHz (5th pass), Polarized beam request
C 30uA @ 250 MHz (5th pass), Polarized beam experiment
D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C
Dec 19 (+holidays): Off, but machine kept in hot standby
Jan 2 (+4 months) - Restart
May 6 (+11 months) -Injector upgrade
UITF
LERF
  • Near and long term goals
GTS
  • TGun status and workload