Fall SAD 2019
Jump to navigation
Jump to search
- Summer Beam Studies
- (not done) Test large shed electrode optics
- Bias anode media:190815_life.pptx
- (done) Bias Gun2 anode during PREX-II
- Fall SAD Planning
- SAD Calendar
- media:190501_GunUpgradeJobs.docx
- media:30July2019_KryptonLine.pptx
- Gun2 Load Lock Chamber Replacement
- 200 kV Gun Tasks
- (done) Remove small shed from UITF and prep for CEBAF
- (done) S&A job for new small shed going into CEBAF
- (done) Pete's BPM Atlis
- (done) Gun2 200kV cathode, 10kV anode, kr plumbing
- 9/19/19 planning meeting media:190918_200keVbeam.docx
- Injector SAD Tasks
- Upgrade the loading chamber
- Upgrade fiber laser connectors req 1 req 2
- Remove oil tank
- Install 2nd decarad unit
- (deferred) Remove, inspect, install FC2
- PQB - SAD & CREX