;CEBAF
 
;CEBAF
 
:Now (+3 wks) - Run A & B
 
:Now (+3 wks) - Run A & B
:Sep 9 (+4 wks) - HV chamber + 200kV beam
+
[[Fall SAD 2019]]
:Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber
+
::Sep 9 (+4 wks) - HV chamber + 200kV beam
:Oct 22 (+3 wks) - HCO
+
::Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber
:Nov 11 (+2 wks) - Restore CEBAF
+
::Oct 22 (+3 wks) - HCO
 +
::Nov 11 (+2 wks) - Restore CEBAF
 
: Nov 25 (+4 wks) Physics @ 2.2 GeV/pass
 
: Nov 25 (+4 wks) Physics @ 2.2 GeV/pass
 
::A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips
 
::A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips
Line 16: Line 17:
 
:May 6 (+11 months) -Injector upgrade
 
:May 6 (+11 months) -Injector upgrade
  
*[[Fall SAD 2019]] Starts September 9
 
 
*[https://accweb.acc.jlab.org/calendar/ Steve's week-by-week calendar]
 
*[https://accweb.acc.jlab.org/calendar/ Steve's week-by-week calendar]
  

Revision as of 07:56, 16 August 2019

We'll meet Friday 8/16 in TL-2236 @ 9:30am

CEBAF
Now (+3 wks) - Run A & B

Fall SAD 2019

Sep 9 (+4 wks) - HV chamber + 200kV beam
Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber
Oct 22 (+3 wks) - HCO
Nov 11 (+2 wks) - Restore CEBAF
Nov 25 (+4 wks) Physics @ 2.2 GeV/pass
A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips
B 100nA @ 250 MHz (5th pass), Polarized beam request
C 30uA @ 250 MHz (5th pass), Polarized beam experiment
D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C
Dec 19 (+holidays): Off, but machine kept in hot standby
Jan 2 (+4 months) - Restart
May 6 (+11 months) -Injector upgrade