Difference between revisions of "August 16, 2019"
Jump to navigation
Jump to search
Line 3: | Line 3: | ||
;CEBAF | ;CEBAF | ||
:Now (+3 wks) - Run A & B | :Now (+3 wks) - Run A & B | ||
− | :Sep 9 (+4 wks) - HV chamber + 200kV beam | + | [[Fall SAD 2019]] |
− | :Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber | + | ::Sep 9 (+4 wks) - HV chamber + 200kV beam |
− | :Oct 22 (+3 wks) - HCO | + | ::Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber |
− | :Nov 11 (+2 wks) - Restore CEBAF | + | ::Oct 22 (+3 wks) - HCO |
+ | ::Nov 11 (+2 wks) - Restore CEBAF | ||
: Nov 25 (+4 wks) Physics @ 2.2 GeV/pass | : Nov 25 (+4 wks) Physics @ 2.2 GeV/pass | ||
::A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips | ::A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips | ||
Line 16: | Line 17: | ||
:May 6 (+11 months) -Injector upgrade | :May 6 (+11 months) -Injector upgrade | ||
− | |||
*[https://accweb.acc.jlab.org/calendar/ Steve's week-by-week calendar] | *[https://accweb.acc.jlab.org/calendar/ Steve's week-by-week calendar] | ||
Revision as of 07:56, 16 August 2019
We'll meet Friday 8/16 in TL-2236 @ 9:30am
- CEBAF
- Now (+3 wks) - Run A & B
- Sep 9 (+4 wks) - HV chamber + 200kV beam
- Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber
- Oct 22 (+3 wks) - HCO
- Nov 11 (+2 wks) - Restore CEBAF
- Nov 25 (+4 wks) Physics @ 2.2 GeV/pass
- A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips
- B 100nA @ 250 MHz (5th pass), Polarized beam request
- C 30uA @ 250 MHz (5th pass), Polarized beam experiment
- D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C
- Dec 19 (+holidays): Off, but machine kept in hot standby
- Jan 2 (+4 months) - Restart
- May 6 (+11 months) -Injector upgrade
- UITF
- Ongoing vacuum work at UITF media:190815_UITFaugust2019.PNG
- Fall plans
- LERF
- Near and long term goals
- GTS
- TGun status and workload