Difference between revisions of "August 16, 2019"
Jump to navigation
Jump to search
Line 8: | Line 8: | ||
::Oct 22 (+3 wks) - HCO | ::Oct 22 (+3 wks) - HCO | ||
::Nov 11 (+2 wks) - Restore CEBAF | ::Nov 11 (+2 wks) - Restore CEBAF | ||
− | + | Nov 25 (+4 wks) Physics @ 2.2 GeV/pass | |
::A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips | ::A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips | ||
::B 100nA @ 250 MHz (5th pass), Polarized beam request | ::B 100nA @ 250 MHz (5th pass), Polarized beam request | ||
::C 30uA @ 250 MHz (5th pass), Polarized beam experiment | ::C 30uA @ 250 MHz (5th pass), Polarized beam experiment | ||
::D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C | ::D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C | ||
− | + | Dec 19 (+holidays): Off, but machine kept in hot standby | |
− | + | Jan 2 (+4 months) - Restart | |
− | + | May 6 (+11 months) -Injector upgrade | |
*[https://accweb.acc.jlab.org/calendar/ Steve's week-by-week calendar] | *[https://accweb.acc.jlab.org/calendar/ Steve's week-by-week calendar] |
Revision as of 07:57, 16 August 2019
We'll meet Friday 8/16 in TL-2236 @ 9:30am
- CEBAF
- Now (+3 wks) - Run A & B
- Sep 9 (+4 wks) - HV chamber + 200kV beam
- Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber
- Oct 22 (+3 wks) - HCO
- Nov 11 (+2 wks) - Restore CEBAF
Nov 25 (+4 wks) Physics @ 2.2 GeV/pass
- A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips
- B 100nA @ 250 MHz (5th pass), Polarized beam request
- C 30uA @ 250 MHz (5th pass), Polarized beam experiment
- D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C
Dec 19 (+holidays): Off, but machine kept in hot standby Jan 2 (+4 months) - Restart May 6 (+11 months) -Injector upgrade
- UITF
- Ongoing vacuum work at UITF media:190815_UITFaugust2019.PNG
- Fall plans
- LERF
- Near and long term goals
- GTS
- TGun status and workload