Difference between revisions of "August 16, 2019"
Jump to navigation
Jump to search
Line 4: | Line 4: | ||
Today...(+3 wks) | Today...(+3 wks) | ||
::Run A & B | ::Run A & B | ||
+ | |||
Sep 9 [[Fall SAD 2019]] | Sep 9 [[Fall SAD 2019]] | ||
::Sep 9 (+4 wks) - HV chamber + 200kV beam | ::Sep 9 (+4 wks) - HV chamber + 200kV beam | ||
Line 9: | Line 10: | ||
::Oct 22 (+3 wks) - HCO | ::Oct 22 (+3 wks) - HCO | ||
::Nov 11 (+2 wks) - Restore CEBAF | ::Nov 11 (+2 wks) - Restore CEBAF | ||
+ | |||
Nov 25 (+4 wks) Physics @ 2.2 GeV/pass | Nov 25 (+4 wks) Physics @ 2.2 GeV/pass | ||
::A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips | ::A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips | ||
Line 14: | Line 16: | ||
::C 30uA @ 250 MHz (5th pass), Polarized beam experiment | ::C 30uA @ 250 MHz (5th pass), Polarized beam experiment | ||
::D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C | ::D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C | ||
+ | |||
Dec 19 (+holidays): Off, but machine kept in hot standby | Dec 19 (+holidays): Off, but machine kept in hot standby | ||
+ | |||
Jan 2 (+4 months) - Restart | Jan 2 (+4 months) - Restart | ||
+ | |||
May 6 (+11 months) -Injector upgrade | May 6 (+11 months) -Injector upgrade | ||
− | |||
− | |||
;UITF | ;UITF |
Revision as of 07:58, 16 August 2019
We'll meet Friday 8/16 in TL-2236 @ 9:30am
- CEBAF
Today...(+3 wks)
- Run A & B
Sep 9 Fall SAD 2019
- Sep 9 (+4 wks) - HV chamber + 200kV beam
- Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber
- Oct 22 (+3 wks) - HCO
- Nov 11 (+2 wks) - Restore CEBAF
Nov 25 (+4 wks) Physics @ 2.2 GeV/pass
- A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips
- B 100nA @ 250 MHz (5th pass), Polarized beam request
- C 30uA @ 250 MHz (5th pass), Polarized beam experiment
- D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C
Dec 19 (+holidays): Off, but machine kept in hot standby
Jan 2 (+4 months) - Restart
May 6 (+11 months) -Injector upgrade
- UITF
- Ongoing vacuum work at UITF media:190815_UITFaugust2019.PNG
- Fall plans
- LERF
- Near and long term goals
- GTS
- TGun status and workload