Difference between revisions of "August 16, 2019"

From Ciswikidb
Jump to navigation Jump to search
 
(6 intermediate revisions by the same user not shown)
Line 2: Line 2:
  
 
;CEBAF
 
;CEBAF
*Schedule on 1 page
+
Today...(+3 wks)
*[[Fall SAD 2019]] Starts September 9
+
::Run A & B
*[https://accweb.acc.jlab.org/calendar/ Steve's week-by-week calendar]
+
 
 +
Sep 9 [[Fall SAD 2019]]
 +
::Sep 9 (+4 wks) - HV chamber + 200kV beam to FC1 (PSS kicker, prebuncher, choppers, buncher, transmission)
 +
::Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber
 +
::Oct 22 (+3 wks) - HCO
 +
::Nov 11 (+2 wks) - Restore CEBAF
 +
 
 +
Nov 25 (+4 wks) Physics @ 2.2 GeV/pass
 +
::A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips
 +
::B 100nA @ 250 MHz (5th pass), Polarized beam request
 +
::C 30uA @ 250 MHz (5th pass), Polarized beam experiment
 +
::D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C
 +
 
 +
Dec 19 (+holidays): Off, but machine kept in hot standby
 +
 
 +
Jan 2 (+4 months) - Restart
 +
 
 +
May 6 (+11 months) -Injector upgrade
  
 
;UITF
 
;UITF

Latest revision as of 08:21, 16 August 2019

We'll meet Friday 8/16 in TL-2236 @ 9:30am

CEBAF

Today...(+3 wks)

Run A & B

Sep 9 Fall SAD 2019

Sep 9 (+4 wks) - HV chamber + 200kV beam to FC1 (PSS kicker, prebuncher, choppers, buncher, transmission)
Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber
Oct 22 (+3 wks) - HCO
Nov 11 (+2 wks) - Restore CEBAF

Nov 25 (+4 wks) Physics @ 2.2 GeV/pass

A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips
B 100nA @ 250 MHz (5th pass), Polarized beam request
C 30uA @ 250 MHz (5th pass), Polarized beam experiment
D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C

Dec 19 (+holidays): Off, but machine kept in hot standby

Jan 2 (+4 months) - Restart

May 6 (+11 months) -Injector upgrade

UITF
LERF
  • Near and long term goals
GTS
  • TGun status and workload