1- New "5 MeV" Dipole update and shielding of Earth's magnetic field
+
1- Bubble Chamber progress at Argonne
Magnet Drawings:
 
  JL0008751_DL_COIL_SPACER.pdf [[media:L0008751_DL_COIL_SPACER.pdf]]
 
  JL0008736_DL_MAGNET_CORE-BOTTOM.pdf [[media:JL0008736_DL_MAGNET_CORE-BOTTOM.pdf]]
 
  JL0008100_DL_MAGNET_COIL.pdf [[media:JL0008100_DL_MAGNET_COIL.pdf]]
 
  JL0011326_DL_TERMINAL_COVER.pdf [[media:L0011326_DL_TERMINAL_COVER.pdf]]
 
  JL0008745_DL_MAGNET_STEEL.pdf [[media:L0008745_DL_MAGNET_STEEL.pdf]]
 
  JL0008102_DL_MAGNET_ASSEMBLY.pdf [[media:JL0008102_DL_MAGNET_ASSEMBLY.pdf]]
 
  JL0008098_DL_MAGNET_CORE-TOP.pdf [[media:JL0008098_DL_MAGNET_CORE-TOP.pdf]]
 
  
 +
2- Bubble Chamber Schedule at JLab
  
2- Can we get a handle on Earth's field by measuring the beam energy simultaneously in the 2D Spectrometer? In this case we need to add another BPM and two Quads (could be weak) to this line.
+
3- How would the 5D beamline look for the Bubble Chamber test in October 2014?
 +
  
3- Bubble Chamber progress at Argonne
 
  
4- Bubble Chamber Schedule at JLab
 
  
5- How would the 5D beamline look for the Bubble Chamber test in October 2014?
+
* Fast Valve was ordered. The Valve will be installed upstream of DP cans. The gauge will be installed at the end of Bubble
  * Fast Valve was ordered. The Valve will be installed upstream of DP cans. The gauge will be installed at the end of Bubble
 
 
  Chamber beamline, in the radiator chamber.
 
  Chamber beamline, in the radiator chamber.

Revision as of 16:36, 5 March 2014

We will meet in TL 2236 on Wednesday March 5 at 3:00 pm EST.

For those calling in we'll use the ReadyTalk audio conference system.

1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada)
2. Enter 7-digit access code 4402297, followed by “#”

Agenda:

1- Bubble Chamber progress at Argonne

2- Bubble Chamber Schedule at JLab

3- How would the 5D beamline look for the Bubble Chamber test in October 2014?



* Fast Valve was ordered. The Valve will be installed upstream of DP cans. The gauge will be installed at the end of Bubble
Chamber beamline, in the radiator chamber.