Difference between revisions of "August 31, 2020 - AIPINJ Phase 1 Planning Meeting"
Jump to navigation
Jump to search
(Created page with "Phase 1 of the injector upgrade begins in a little more than 3 weeks. The layout is final, the design work is ramping down. Daily jobs involve fabrication, assembly and tes...") |
|||
(One intermediate revision by the same user not shown) | |||
Line 5: | Line 5: | ||
We'll do the following... | We'll do the following... | ||
− | ::( | + | ::(20 min) Overview of beam line [[media:200821_Songsheet.pdf]] |
− | ::( | + | ::(20 min) Status of elements [[media:200827_AIPINJ_layout_rev5.xlsx]] |
+ | ::(20 min) Discussion of draft schedule [[media:200826_AIPINJ_Schedule.xlsx]] |
Latest revision as of 12:15, 27 August 2020
Phase 1 of the injector upgrade begins in a little more than 3 weeks. The layout is final, the design work is ramping down. Daily jobs involve fabrication, assembly and testing. Integration with out groups and the SAD calendar is ramping up.
- Blue jeans link : https://bluejeans.com/909497334
We'll do the following...
- (20 min) Overview of beam line media:200821_Songsheet.pdf
- (20 min) Status of elements media:200827_AIPINJ_layout_rev5.xlsx
- (20 min) Discussion of draft schedule media:200826_AIPINJ_Schedule.xlsx