# First commissioning of water irradiation beamline in May??? (goal) | # First commissioning of water irradiation beamline in May??? (goal) | ||
− | ==== <u>Engineering | + | ==== <u>Engineering:</u> ==== |
− | + | ''EES-RF:'' Troubleshooting Booster behavior | |
− | + | ''EES-DC:'' QD/QJ quads okay by Meyers for no water cooling up to 10A (revisit if fields higher than that are required) | |
− | + | ''SSG:'' Known MPS nodes to add: | |
#* Fast valve | #* Fast valve | ||
#* Solenoid current window comparator (perhaps needed?, worst case: small window temp rise) | #* Solenoid current window comparator (perhaps needed?, worst case: small window temp rise) | ||
#* BCM over current trip set point. MPS/PSS BCM similar to CEBAF injector; find receiver and determine implementation at UITF | #* BCM over current trip set point. MPS/PSS BCM similar to CEBAF injector; find receiver and determine implementation at UITF | ||
− | + | ''EES-IC:'' [[media: I&C tasks ver1.docx]] | |
#*Action item: List all the tasks we have for Engineering: I&C, DC power, SSG and provide as much notice as possible. [McCaughan] | #*Action item: List all the tasks we have for Engineering: I&C, DC power, SSG and provide as much notice as possible. [McCaughan] |
Revision as of 13:02, 13 January 2021
Meeting Information
The meeting will be on Thursday January 14, 2020 at 2:00 PM EDT.
Connecting
To connect to the meeting, please do the following:
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Rough timetable:
- Until CMTF testing: UITF will be locked up daily to improve the rf performance of the booster, measure optics, learn how to beta-match across the booster, etc.
- CMTF tests with C75-1 (~mid-Mar- mid-Apr). Gigi: CMTF schedule / testing duration
- UITF beamline Modification in parallel to install new beamline
- First commissioning of water irradiation beamline in May??? (goal)
Engineering:
EES-RF: Troubleshooting Booster behavior
EES-DC: QD/QJ quads okay by Meyers for no water cooling up to 10A (revisit if fields higher than that are required)
SSG: Known MPS nodes to add:
- Fast valve
- Solenoid current window comparator (perhaps needed?, worst case: small window temp rise)
- BCM over current trip set point. MPS/PSS BCM similar to CEBAF injector; find receiver and determine implementation at UITF
EES-IC: media: I&C tasks ver1.docx