''SSG:'' Known MPS nodes to add: | ''SSG:'' Known MPS nodes to add: | ||
− | + | * Fast valve | |
− | + | * Solenoid current window comparator (perhaps needed?, worst case: small window temp rise) | |
− | + | * BCM over current trip set point. MPS/PSS BCM similar to CEBAF injector; find receiver and determine implementation at UITF | |
''EES-IC:'' [[media: I&C tasks ver1.docx]] | ''EES-IC:'' [[media: I&C tasks ver1.docx]] | ||
− | + | *'''<u>New Action item:</u>''' List all the tasks we have for Engineering: I&C, DC power, SSG and provide as much notice as possible. [McCaughan] | |
[[Meeting_minutes | Back to Main Meeting Minutes Page]] | [[Meeting_minutes | Back to Main Meeting Minutes Page]] |
Revision as of 13:05, 13 January 2021
Meeting Information
The meeting will be on Thursday January 14, 2020 at 2:00 PM EDT.
Connecting
To connect to the meeting, please do the following:
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Rough timetable:
- Until CMTF testing: UITF will be locked up daily to improve the rf performance of the booster, measure optics, learn how to beta-match across the booster, etc.
- CMTF tests with C75-1 (~mid-Mar- mid-Apr). Gigi: CMTF schedule / testing duration
- UITF beamline Modification in parallel to install new beamline
- First commissioning of water irradiation beamline in May??? (goal)
Engineering:
EES-RF: Troubleshooting Booster behavior (Status Update)
EES-DC: QD/QJ quads okay by Meyers for no water cooling up to 10A (revisit if fields higher than that are required)
SSG: Known MPS nodes to add:
- Fast valve
- Solenoid current window comparator (perhaps needed?, worst case: small window temp rise)
- BCM over current trip set point. MPS/PSS BCM similar to CEBAF injector; find receiver and determine implementation at UITF
EES-IC: media: I&C tasks ver1.docx
- New Action item: List all the tasks we have for Engineering: I&C, DC power, SSG and provide as much notice as possible. [McCaughan]