Difference between revisions of "March 1, 2021 - DC/Magnet Installation Kickoff"
Jump to navigation
Jump to search
(7 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
= Meeting Info == | = Meeting Info == | ||
− | + | We will kick-off the Phase 1 magnet installation following Steve's Monday at 1330 SAD discussion. https://bluejeans.com/569476853 | |
− | |||
− | |||
== Agenda == | == Agenda == | ||
Line 8: | Line 6: | ||
; Installation status | ; Installation status | ||
* Schedule | * Schedule | ||
− | **Transition from vac/mech to girder hook-ups planned to begin April 5 ('''5 weeks from today''') | + | **Transition from vac/mech to girder hook-ups planned to begin April 5 ('''5 weeks from today''') - maybe 1 or 2 weeks earlier |
− | + | **'''4 weeks (Apr 5 - Apr 30)''' are allocated for girder hook-ups + HCO/System readiness for everything up to FC#2 | |
− | ** | ||
− | |||
− | * | + | *Beam line layout |
− | ** | + | ** Preliminary ME songsheet released, up to date as of '''Feb 23''' on the upgrade home page => [[CEBAF Injector Upgrade]] |
− | + | ** 3D CAD model exists if you want to see something not there now | |
+ | ** Cables: Like before trays (above & on girder) + 3 cable bundle drops (near Y, Laser, Chopper) | ||
; DC/Magnet Jobs | ; DC/Magnet Jobs | ||
− | * | + | * Spreadsheet with magnet information updated as of '''Mar 1''' [[media:210301_Phase1_Magnet_Summary.xlsx]] |
− | |||
− | |||
− | |||
; Software Jobs | ; Software Jobs | ||
Line 30: | Line 24: | ||
; Other magnet jobs | ; Other magnet jobs | ||
− | *(JM) Complete magnet table I circulated | + | * '''Done''' (JM) Complete magnet table I circulated |
*(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary | *(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary | ||
*(RS/GC) FG solenoid special hysteresis for Gary | *(RS/GC) FG solenoid special hysteresis for Gary | ||
Line 43: | Line 37: | ||
*(LL) Report on PSS kicker | *(LL) Report on PSS kicker | ||
− | ; CIS Jobs | + | ; CIS Magnet Jobs |
− | * | + | * [[Phase 1 - HCO & Commissioning]] |
; Plans | ; Plans | ||
* Jobs list => Phase 1 area on the upgrade home page => [[CEBAF Injector Upgrade]] | * Jobs list => Phase 1 area on the upgrade home page => [[CEBAF Injector Upgrade]] | ||
* Meet in 2 weeks? | * Meet in 2 weeks? |
Latest revision as of 14:53, 1 March 2021
Meeting Info =
We will kick-off the Phase 1 magnet installation following Steve's Monday at 1330 SAD discussion. https://bluejeans.com/569476853
Agenda
- Installation status
- Schedule
- Transition from vac/mech to girder hook-ups planned to begin April 5 (5 weeks from today) - maybe 1 or 2 weeks earlier
- 4 weeks (Apr 5 - Apr 30) are allocated for girder hook-ups + HCO/System readiness for everything up to FC#2
- Beam line layout
- Preliminary ME songsheet released, up to date as of Feb 23 on the upgrade home page => CEBAF Injector Upgrade
- 3D CAD model exists if you want to see something not there now
- Cables: Like before trays (above & on girder) + 3 cable bundle drops (near Y, Laser, Chopper)
- DC/Magnet Jobs
- Spreadsheet with magnet information updated as of Mar 1 media:210301_Phase1_Magnet_Summary.xlsx
- Software Jobs
- CED
- Apps
- Screens
- What else for software?
- Other magnet jobs
- Done (JM) Complete magnet table I circulated
- (JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
- (RS/GC) FG solenoid special hysteresis for Gary
- (RS/MJ) Magnet info for Inj Steer spin calculations
- (JM/JG) Decision on spare DR fabrication and alignment
- (LL/JK/JM) PSS kicker - does MMF have any responsibility here, maybe just PSS?
- (LL/JM) Second QW measurement, what's the scope here?
- (JM) When is the rotating coil stand ready?
- (JM/LL) Reconciling MHD discrepancy
- (LL) Report on QW
- (LL) Report on HD
- (LL) Report on PSS kicker
- CIS Magnet Jobs
- Plans
- Jobs list => Phase 1 area on the upgrade home page => CEBAF Injector Upgrade
- Meet in 2 weeks?