Difference between revisions of "NEG coated 2.5 inch OD BPM's"
Jump to navigation
Jump to search
Line 1: | Line 1: | ||
− | + | 200 KV BPM's with NEG coating | |
== ME Design == | == ME Design == | ||
− | *weldment [[media:JL0091130-0114 BPM TUBE WELDMENT, REV-.pdf]] | + | * can weldment [[media:JL0091130-0114 BPM TUBE WELDMENT, REV-.pdf]] |
+ | * final assembly drawing coming from danny | ||
== Assembly Sequence == | == Assembly Sequence == | ||
Line 18: | Line 19: | ||
== Gabou Measurements == | == Gabou Measurements == | ||
− | * Summary (see NEG BPM) - [[media:UITF_SPM_Summary_9_21.ods]] | + | * Summary (see NEG BPM 1-4) - [[media:UITF_SPM_Summary_9_21.ods]] |
* NEG BPM #1 - [[media:NEG_1_1cmx2cm_lower.pdf]] | * NEG BPM #1 - [[media:NEG_1_1cmx2cm_lower.pdf]] | ||
* NEG BPM #2 - [[media:NEG_2_1cmx2cm_upper.pdf]], [[media:NEG_2_1cmx2cm_boresight.pdf]] | * NEG BPM #2 - [[media:NEG_2_1cmx2cm_upper.pdf]], [[media:NEG_2_1cmx2cm_boresight.pdf]] | ||
* NEG BPM #3 | * NEG BPM #3 | ||
* NEG BPM #4 | * NEG BPM #4 |
Revision as of 16:14, 14 June 2021
200 KV BPM's with NEG coating
ME Design
- can weldment media:JL0091130-0114 BPM TUBE WELDMENT, REV-.pdf
- final assembly drawing coming from danny
Assembly Sequence
- Receive can/feedthroughs
- Clean
- Degas
- NEG Coat
- Check feedthroughs
- Assemble feedthroughs
- serialize
- Leak check cans
- electrical measurement
- report K's and center
Gabou Measurements
- Summary (see NEG BPM 1-4) - media:UITF_SPM_Summary_9_21.ods
- NEG BPM #1 - media:NEG_1_1cmx2cm_lower.pdf
- NEG BPM #2 - media:NEG_2_1cmx2cm_upper.pdf, media:NEG_2_1cmx2cm_boresight.pdf
- NEG BPM #3
- NEG BPM #4