+ | * [https://logbooks.jlab.org/entry/3883030 Harp and NEG installed in MeV Spectrometer Line] | ||
+ | * Corrector / Raster installation - completed; turned over to EES-DC/Gunning | ||
+ | * Build 80/20 support structure for Pb (Completed) | ||
+ | * Pb stacked; some modification possibly required. RCG/ME discussing. | ||
+ | * Install target mechanism (Completed) - Survey required | ||
* EES may start cabling downstream section & making UED updates. | * EES may start cabling downstream section & making UED updates. | ||
* Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining. | * Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining. | ||
* [[media:Engineering-support-jobs.docx| List of Engineering Jobs remaining]] | * [[media:Engineering-support-jobs.docx| List of Engineering Jobs remaining]] | ||
− | + | Gun work progressing well: | |
− | + | * [https://logbooks.jlab.org/entry/3882796 HVPS SF6 leak quantified] | |
− | * | + | * [https://logbooks.jlab.org/entry/3882992 S&A report post gun electrode alignment] |
+ | * [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule] | ||
<u>Still to do:</u> | <u>Still to do:</u> | ||
− | |||
− | |||
− | |||
* Add Mu metal over bellows on wastewater line. | * Add Mu metal over bellows on wastewater line. | ||
Revision as of 10:36, 19 July 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- Supplementary Shielding Installation: ???
- Beamline Commissioning / Test Plans / Shielding Verification
- 7/26/21 Start Hot Check-out
- Commission new beam line and execute experiment
- Science!!!
New items for discussion:
Short term schedule update:
This week:
- Harp and NEG installed in MeV Spectrometer Line
- Corrector / Raster installation - completed; turned over to EES-DC/Gunning
- Build 80/20 support structure for Pb (Completed)
- Pb stacked; some modification possibly required. RCG/ME discussing.
- Install target mechanism (Completed) - Survey required
- EES may start cabling downstream section & making UED updates.
- Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.
- List of Engineering Jobs remaining
Gun work progressing well:
Still to do:
- Add Mu metal over bellows on wastewater line.
Next Week:
- Mount bottle rack in Labyrinth (Staged); remove gas bottles to rack.
- Unistrut mounting for cables - Neal will do when available
- Engineering work on beam line starting
2 weeks:
- Pull Heliax from Spectrum analyzer/Control room >> Buncher
- 4th terminal system in Control room under assembly/rebuild
- Items from To-do list...
Engineering Other business
Reports on Open Action Items:
Action Items:
- Formal run plan (McCaughan) Strawman