Difference between revisions of "2021-07-21"
Jump to navigation
Jump to search
(Created page with "== Meeting Information == ==== Connecting ==== To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST. # To join via a Web Browser, go to the pag...") |
|||
Line 13: | Line 13: | ||
==== <u>Schedule</u> ==== | ==== <u>Schedule</u> ==== | ||
Long Term Schedule: [[Media:WW-Install_6.22.21.pdf|Gantt]] ([[Media:WW-ToDo_6.22.21.pdf|Outstanding tasks]]) | Long Term Schedule: [[Media:WW-Install_6.22.21.pdf|Gantt]] ([[Media:WW-ToDo_6.22.21.pdf|Outstanding tasks]]) | ||
− | |||
− | |||
# 7/26/21 Start Hot Check-out | # 7/26/21 Start Hot Check-out | ||
− | + | ||
− | + | ||
==== <u>New items for discussion:</u> ==== | ==== <u>New items for discussion:</u> ==== | ||
<u>Short term schedule update:</u><br> | <u>Short term schedule update:</u><br> | ||
<u>This week:</u> | <u>This week:</u> | ||
− | * [https://logbooks.jlab.org/entry/ | + | * [https://logbooks.jlab.org/entry/3884298 Spectrometer pumps on EPICs], [https://logbooks.jlab.org/entry/3884303 Turbo disconnected] |
* [https://logbooks.jlab.org/entry/3883526 Corrector installation & cable reroute mostly complete], turned over to DC power | * [https://logbooks.jlab.org/entry/3883526 Corrector installation & cable reroute mostly complete], turned over to DC power | ||
− | * [https://logbooks.jlab.org/entry/ | + | * [https://logbooks.jlab.org/entry/3884311 BPMs connections good - save iocipmm904 removal - iocipmm901 installed in its place] |
+ | * [https://logbooks.jlab.org/entry/3885222 Nomenclature for elements disseminated and labelled] | ||
* Raster installation - completed; turned over to Bill Gunning | * Raster installation - completed; turned over to Bill Gunning | ||
+ | * Install target mechanism (Completed), [https://logbooks.jlab.org/entry/3884440 motor controls tested] - Survey required | ||
* Build 80/20 support structure for Pb (Completed) | * Build 80/20 support structure for Pb (Completed) | ||
* Pb stacked; some modification possibly required. RCG/ME discussing. | * Pb stacked; some modification possibly required. RCG/ME discussing. | ||
− | + | * EES work happening in earnest | |
− | * EES | ||
* Ready to install Al base plates for FC3 region rework as well as solenoid stand. [https://logbooks.jlab.org/entry/3883262 80/20 reworked for support] | * Ready to install Al base plates for FC3 region rework as well as solenoid stand. [https://logbooks.jlab.org/entry/3883262 80/20 reworked for support] | ||
* [[media:Engineering-support-jobs.docx| List of Engineering Jobs remaining]] | * [[media:Engineering-support-jobs.docx| List of Engineering Jobs remaining]] | ||
Gun work progressing well: | Gun work progressing well: | ||
− | * [https://logbooks.jlab.org/entry/ | + | * [https://logbooks.jlab.org/entry/3884328 Gun/Depo chamber bake started] and [https://logbooks.jlab.org/entry/3885376 completed] |
− | + | ||
* [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule] | * [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule] | ||
Revision as of 10:51, 19 July 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- 7/26/21 Start Hot Check-out
New items for discussion:
Short term schedule update:
This week:
- Spectrometer pumps on EPICs, Turbo disconnected
- Corrector installation & cable reroute mostly complete, turned over to DC power
- BPMs connections good - save iocipmm904 removal - iocipmm901 installed in its place
- Nomenclature for elements disseminated and labelled
- Raster installation - completed; turned over to Bill Gunning
- Install target mechanism (Completed), motor controls tested - Survey required
- Build 80/20 support structure for Pb (Completed)
- Pb stacked; some modification possibly required. RCG/ME discussing.
- EES work happening in earnest
- Ready to install Al base plates for FC3 region rework as well as solenoid stand. 80/20 reworked for support
- List of Engineering Jobs remaining
Gun work progressing well:
Still to do:
- Add Mu metal over bellows on wastewater line.
Next Week:
- Mount bottle rack in Labyrinth (Staged); remove gas bottles to rack.
- Unistrut mounting for cables - Neal will do when available
- Engineering work on beam line starting
2 weeks:
- Pull Heliax from Spectrum analyzer/Control room >> Buncher
- 4th terminal system in Control room under assembly/rebuild
- Items from To-do list...
Engineering Other business
Reports on Open Action Items:
Action Items:
- Formal run plan (McCaughan) Strawman