+ | '''Timeline 2022''' | ||
+ | *April - finish design & assembly of Wien and Mott hardware, finish 200 KV HV vac work | ||
+ | *May - install Wien/Mott UITF, finish 200 KV gun assembly, restore polarized laser UITF | ||
+ | *June - install 200 keV gun, bake, big job, goal is making beam by ~July 4th weekend | ||
+ | *July - make 200 keV polarized beam, calibrate the Mott, using ~nA beam and U-Wien | ||
+ | *Aug - install Compton in MeV section, run keV beam as needed | ||
+ | *Sep/Oct - calibrate Compton, two separate ~week long runs | ||
+ | |||
+ | |||
+ | * [[File:200kV Gun w-CIS-ASY-R30-3 (2) iso.png]] | ||
+ | |||
* <span style="font-size:100%"> '''[[Background and status as of July 1 2021]]''' </span> | * <span style="font-size:100%"> '''[[Background and status as of July 1 2021]]''' </span> | ||
Line 9: | Line 20: | ||
* <span style="font-size:100%"> '''[[Electrostatic and beam dynamics simulations]]''' </span> | * <span style="font-size:100%"> '''[[Electrostatic and beam dynamics simulations]]''' </span> | ||
− | + | * <span style="font-size:100%"> '''[[Update meetings]]''' </span> | |
− | * | + | |
− | + | * <span style="font-size:100%"> '''[[Presentations]]''' </span> | |
− | |||
− | * | ||
− | |||
− | |||
− | |||
− |
Revision as of 09:40, 31 March 2022
Timeline 2022
- April - finish design & assembly of Wien and Mott hardware, finish 200 KV HV vac work
- May - install Wien/Mott UITF, finish 200 KV gun assembly, restore polarized laser UITF
- June - install 200 keV gun, bake, big job, goal is making beam by ~July 4th weekend
- July - make 200 keV polarized beam, calibrate the Mott, using ~nA beam and U-Wien
- Aug - install Compton in MeV section, run keV beam as needed
- Sep/Oct - calibrate Compton, two separate ~week long runs