Difference between revisions of "18" Photogun ala GTS"

From Ciswikidb
Jump to navigation Jump to search
Line 1: Line 1:
 +
'''Timeline 2022'''
 +
*April - finish design & assembly of Wien and Mott hardware, finish 200 KV HV vac work
 +
*May - install Wien/Mott UITF, finish 200 KV gun assembly, restore polarized laser UITF
 +
*June - install 200 keV gun, bake, big job, goal is making beam by ~July 4th weekend
 +
*July - make 200 keV polarized beam, calibrate the Mott, using ~nA beam and U-Wien
 +
*Aug - install Compton in MeV section, run keV beam as needed
 +
*Sep/Oct - calibrate Compton, two separate ~week long runs
 +
 +
 
* [[File:200kV Gun w-CIS-ASY-R30-3 (2) iso.png]]
 
* [[File:200kV Gun w-CIS-ASY-R30-3 (2) iso.png]]
  

Revision as of 08:40, 31 March 2022

Timeline 2022

  • April - finish design & assembly of Wien and Mott hardware, finish 200 KV HV vac work
  • May - install Wien/Mott UITF, finish 200 KV gun assembly, restore polarized laser UITF
  • June - install 200 keV gun, bake, big job, goal is making beam by ~July 4th weekend
  • July - make 200 keV polarized beam, calibrate the Mott, using ~nA beam and U-Wien
  • Aug - install Compton in MeV section, run keV beam as needed
  • Sep/Oct - calibrate Compton, two separate ~week long runs


  • 200kV Gun w-CIS-ASY-R30-3 (2) iso.png