(Created page with "* Remove WP-1250 NEG cartridges * Remove posts for woven metal screen and replace with something suitable for high vacuum * Add (tack weld?) fixtures to the vacuum chamber fo...") |
|||
(One intermediate revision by one other user not shown) | |||
Line 1: | Line 1: | ||
+ | |||
+ | == Done == | ||
+ | |||
* Remove WP-1250 NEG cartridges | * Remove WP-1250 NEG cartridges | ||
* Remove posts for woven metal screen and replace with something suitable for high vacuum | * Remove posts for woven metal screen and replace with something suitable for high vacuum | ||
Line 12: | Line 15: | ||
** Devise a reliable method to prevent electrical short in the NEG cartridges electrical connections for full activation with current | ** Devise a reliable method to prevent electrical short in the NEG cartridges electrical connections for full activation with current | ||
* Re-install extractor gauge | * Re-install extractor gauge | ||
+ | |||
+ | |||
+ | == vacuum qualification of chamber == | ||
+ | * Gun chamber cleaned, blown down with ionized nitrogen | ||
+ | * UHV1400 pumps installed and connected to feedthrough | ||
+ | * First bake: 48 hours at 250C. No NEG activation. Leak in extractor gauge opened on ramp down | ||
+ | * Second bake: 24 hours at 250C after vent for extractor swap. P vs. T data taken for ~2 weeks | ||
+ | * Third bake: 48 hours at 250C, NEG activated for 1 hour at 500C while chamber at 200C. Vacuum tests underway 31march2022 | ||
+ | |||
+ | |||
+ | == Steps for completion == | ||
+ | * Finish vacuum qualification (~April 15) | ||
+ | * Fabricate and install shield screen | ||
+ | ** Finalize design (April 8) | ||
+ | ** Order parts: standoffs, more screen, shimstock strips? (April 8) | ||
+ | ** clean and heat treat materials (April 18 or 25) | ||
+ | ** install screen (April 25 or May 2) | ||
+ | * Send gun assembly to clean room for inversion, nitrogen blow-down. week of May 2? | ||
+ | * Install spider and anode, align | ||
+ | * Install electrode, align | ||
+ | |||
+ | |||
+ | |||
+ | [https://wiki.jlab.org/ciswiki/index.php/18%22_Photogun_ala_GTS Back to 18" Photogun page] |
Latest revision as of 11:36, 31 March 2022
Done
- Remove WP-1250 NEG cartridges
- Remove posts for woven metal screen and replace with something suitable for high vacuum
- Add (tack weld?) fixtures to the vacuum chamber for S&A tooling
- Send vacuum chamber to S&A for fiducial (locate top flange, and anode flange with repost to chamber z-axis.
- Clean vacuum chamber (wipe off with iso-propanol, removed foreign objects, etc)
- Consider replacing the WP-1250 NEG cartridges with modern UHV 1400 NEG wafer modules (~12 week delivery)
- If using UHV 1400 NEG wafer modules, no screen is necessary
- Marcy to calculate how many UHV 1400 NEG wafer modules are needed, based on this, we'll develop a scheme to mount them. No need for a shield screen if e go with this modern NEG wafer modules. Need to figure out how to win them inside the vacuum chamber, and likely built a new power supply.
- If the old WP-1250 modules stay:
- Bubba to finish new woven metal screen
- Devise a better method to hold the screen in place
- Devise a reliable method to prevent electrical short in the NEG cartridges electrical connections for full activation with current
- Re-install extractor gauge
vacuum qualification of chamber
- Gun chamber cleaned, blown down with ionized nitrogen
- UHV1400 pumps installed and connected to feedthrough
- First bake: 48 hours at 250C. No NEG activation. Leak in extractor gauge opened on ramp down
- Second bake: 24 hours at 250C after vent for extractor swap. P vs. T data taken for ~2 weeks
- Third bake: 48 hours at 250C, NEG activated for 1 hour at 500C while chamber at 200C. Vacuum tests underway 31march2022
Steps for completion
- Finish vacuum qualification (~April 15)
- Fabricate and install shield screen
- Finalize design (April 8)
- Order parts: standoffs, more screen, shimstock strips? (April 8)
- clean and heat treat materials (April 18 or 25)
- install screen (April 25 or May 2)
- Send gun assembly to clean room for inversion, nitrogen blow-down. week of May 2?
- Install spider and anode, align
- Install electrode, align