Difference between revisions of "Meeting 7/7/22 - COMTRA"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "; Thursday's @ 9am EDT by Zoom * Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09 * Zoom ID: 160 190 6056 and Passcode: 99...")
 
 
(4 intermediate revisions by the same user not shown)
Line 2: Line 2:
 
* Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
 
* Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
 
* Zoom ID: 160 190 6056 and Passcode: 992019
 
* Zoom ID: 160 190 6056 and Passcode: 992019
* Meeting wiki - https://wiki.jlab.org/ciswiki/index.php/Meeting_6/29/22_-_COMTRA
+
* Meeting wiki - https://wiki.jlab.org/ciswiki/index.php/Meeting_7/7/22_-_COMTRA
  
===6/30/22 Updates...===
+
===7/7/22 Update===
  
;ME
+
;Analyzing Magnet
* Stands - UITF: Purchase order placed.   BNL: ?
+
* PS (due 7/15) => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
* Collimator - Last week Riad provided drawing, found material but does not know if OHFC.   Need (2) per this drawing.  [[media:JL0015777_Cu_collimator.pdf]]  '''What about ID hole???'''
+
* Magnet (request 7/15) => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
* Absorbers - Christine provided drawing 6/3, I forgot to act on this!  Need (6) per this drawing => [[media:Absorber - 240 D 001 14_V4.pdf]]
 
  
;Analyzing Magnet
+
;DAQ & RACK
* Power supply with ethernet and rack mount option - PR 6/9, PO 6/13, request 6/24 => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
+
* PMT-5R ItoV amplifier (due TBD)
* Magnet winding around JLab machined cores - PR 5/31, PO 6/2, request 7/15 => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
+
* To-do => final cable, connector, rack layout
* Model development => 6/27 Probir provided magnetic model to Greg.  Eric, can you outline how we used magnet model for PEPPo AM in Geant (to assign B-field in air/magnet, P-field in iron core)?
 
  
 
;Detector
 
;Detector
 
* BGO crystals - Arrived at JLab, stored in cabinet
 
* BGO crystals - Arrived at JLab, stored in cabinet
* PMT status - (4) Hamamatsu tubes w/ magnetic shield, PR 6/1, PO 6/2, due 8/2 or earlier => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412467
+
* PMTs (due 8/2) => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412467
* PMT base status?
+
* PMT bases (due 8/1-9/15)
* Detector box status?
+
* Detector boxes (ship by 8/1)
 +
 
 +
;ME
 +
* UITF Stand - PR placed due 7/20 - https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1
 +
* BNL Stand - agreed w/ Cliff, will work up the order
 +
* Collimator - Fabricate (2) [[media:JL0015777_Cu_collimator.pdf]] => CIS drop off
 +
* Absorbers - Fabricate (6) [[media:Absorber - 240 D 001 14_V4.pdf]] => CIS drop off
  
;DAQ
+
;Geant4 Model
* PMT-5R ItoV amplifier with remote control - 6/23 CC order placed to Advanced Instruments Corp, delivery date TBD
+
* Adding magnetic model
* Rack- Last week? we discussed a rack layout showing all components + add/list odds/ends still needed UITF cables, connectors, patch panel, lifting bolts?, wheels?, can we finalize/order these
+
* Simulation study (due 7/14?)
* Rest of DAQ (hardware and software) - how are we looking for UITF readiness ... Like = Aug 1, Should = Sep 1, Must = Oct 1
 
  
 
;Documentation
 
;Documentation
* NIM paper - 6/29 created overleaf folder with Elsevier Article (elsarticle) template, will share after framing outline => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
+
* NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
* Portable Compton Polarimeter Manual - Still TBD, ideas how to outline this one?  Do in Overleaf too, or is a Sharepoint Word file better for drag/drop, everyone, etc?
+
* Manual - Sharepoint
 
 
;Greg's weekly meeting
 
* Geant4 simulations - Joe/Eric/Riad ? and when ?
 

Latest revision as of 10:02, 10 July 2022

Thursday's @ 9am EDT by Zoom

7/7/22 Update

Analyzing Magnet
DAQ & RACK
  • PMT-5R ItoV amplifier (due TBD)
  • To-do => final cable, connector, rack layout
Detector
ME
Geant4 Model
  • Adding magnetic model
  • Simulation study (due 7/14?)
Documentation