Difference between revisions of "Meeting 9/15/22 - COMTRA"
Jump to navigation
Jump to search
(Created page with ";Thursday's @ 9am EDT by Zoom * Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09 * Zoom ID: 160 190 6056 and Passcode: 992...") |
|||
(5 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
* Zoom ID: 160 190 6056 and Passcode: 992019 | * Zoom ID: 160 190 6056 and Passcode: 992019 | ||
− | === | + | == Readiness Updates == |
− | |||
− | |||
− | + | * Tour of installation so far [[media:220914_COMTRA.pptx]] | |
* ME/Layout | * ME/Layout | ||
Line 15: | Line 13: | ||
* Experiment components | * Experiment components | ||
− | ** collimator installed and | + | ** collimator installed and aligned |
** magnet measurement, status for install | ** magnet measurement, status for install | ||
** detector assembly, fiducialization | ** detector assembly, fiducialization | ||
Line 27: | Line 25: | ||
* DAQ/Controls | * DAQ/Controls | ||
+ | ** Helicity generator | ||
+ | ** High Voltage | ||
+ | ** EFADC/DAQ | ||
+ | ** Kepco PS | ||
+ | |||
+ | * Experiment sequence | ||
+ | ** Pre-Beam - complete HCO, magnet ready, assembly detector ready, fiducial them, mock-up install ?, remove temporarily | ||
+ | ** Commission - setup beam to FCUP, APERTURE, DUMP and use x-ray card to define orbit to collimator | ||
+ | ** Experiment - install/align magnet/detector (w/ attenuators?), deliver x-rays, optimize DAQ, measure asymmetry vs. XYZ and with Wien | ||
+ | |||
+ | |||
+ | == Older Links== | ||
+ | * UITFList Links | ||
+ | ** General COMTRA installation => https://tasklists.jlab.org/uitflist/tasks/107371 | ||
+ | ** DC power magnet install => https://tasklists.jlab.org/uitflist/tasks/107370 | ||
− | + | *Beamline | |
− | * Layout for RadCon [[media:Compton Layout for Radcon Shielding 8-10-22-3.pptx]] | + | ** Layout for RadCon [[media:Compton Layout for Radcon Shielding 8-10-22-3.pptx]] |
− | * Spool flanges [[media:Flanges and Reducer for Compton and RF Kicker-jmg.xlsx]] | + | ** Spool flanges [[media:Flanges and Reducer for Compton and RF Kicker-jmg.xlsx]] |
− | * Radiator - (1) on-hand, '''(1) need for BNL''' [[media:IMG_20220804_084829378.jpg|thumb]] | + | ** Radiator - (1) on-hand, '''(1) need for BNL''' [[media:IMG_20220804_084829378.jpg|thumb]] |
− | * | + | ** Lead for UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 [[media:IMG_20220804_084121573.jpg|thumb]] |
− | * Lead for UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 [[media:IMG_20220804_084121573.jpg|thumb]] | ||
− | + | *Magnet | |
− | * Kepco PS - '''ship 8/31 2 day air''' => [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686 PR] | + | ** Kepco PS - '''ship 8/31 2 day air''' => [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686 PR] |
− | * Magnet [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389 EMC PR#1][https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=414754 PR#2] [[media:220810_Magnet.jpg|coil thumb]] | + | ** Magnet [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389 EMC PR#1][https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=414754 PR#2] [[media:220810_Magnet.jpg|coil thumb]] |
− | + | *Detector | |
− | * Bases - '''due 9/15 - comes with Thi in September''' | + | ** Bases - '''due 9/15 - comes with Thi in September''' |
− | * Collimator - (2) on-hand [[media:JL0015777_Cu_collimator.pdf]] [[media:IMG_20220804_082153706.jpg|thumb]] | + | ** Collimator - (2) on-hand [[media:JL0015777_Cu_collimator.pdf]] [[media:IMG_20220804_082153706.jpg|thumb]] |
− | * Absorbers - (6) on-hand [[media:Absorber - 240 D 001 14_V4.pdf]] [[media:IMG_20220804_082037794.jpg|thumb]] | + | ** Absorbers - (6) on-hand [[media:Absorber - 240 D 001 14_V4.pdf]] [[media:IMG_20220804_082037794.jpg|thumb]] |
− | * Boxes - (2) on hand [[media:IMG_20220808_132907716.jpg|thumb]] | + | ** Boxes - (2) on hand [[media:IMG_20220808_132907716.jpg|thumb]] |
− | * BGO - (2) on-hand [[media:IMG_20220804_084436318.jpg|thumb]] [[media:IMG_20220811_154533240.jpg|thumb]] [[media:IMG_20220811_154547652.jpg|thumb]] [[media:IMG_20220811_154606586.jpg|thumb]] [[media:IMG_20220811_154619455.jpg|thumb]] | + | ** BGO - (2) on-hand [[media:IMG_20220804_084436318.jpg|thumb]] [[media:IMG_20220811_154533240.jpg|thumb]] [[media:IMG_20220811_154547652.jpg|thumb]] [[media:IMG_20220811_154606586.jpg|thumb]] [[media:IMG_20220811_154619455.jpg|thumb]] |
− | * PMT and mu shields - (4) on-hand [[media:IMG_20220804_081738760.jpg|thumb]] | + | ** PMT and mu shields - (4) on-hand [[media:IMG_20220804_081738760.jpg|thumb]] |
− | + | *Documentation | |
− | * NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a | + | ** NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a |
− | * Manual - Sharepoint | + | ** Manual - Sharepoint |
Latest revision as of 18:40, 14 September 2022
- Thursday's @ 9am EDT by Zoom
- Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
- Zoom ID: 160 190 6056 and Passcode: 992019
Readiness Updates
- Tour of installation so far media:220914_COMTRA.pptx
- ME/Layout
- updated songsheet and quick reference, matching UED
- dimensions when needed for S&A or Greg's Geant4 model
- RadCon approval for lead wall, and experiment hut
- Experiment components
- collimator installed and aligned
- magnet measurement, status for install
- detector assembly, fiducialization
- I&C jobs
- Remote motion control for aperture (otherwise do by hand w/ access)
- Attach current monitors to aperture and dump
- Plumb LCW for current monitor and dump
- Pull 6 fibers from DAQ to mezzanine
- Align x-ray camera for x-ray card after collimator
- DAQ/Controls
- Helicity generator
- High Voltage
- EFADC/DAQ
- Kepco PS
- Experiment sequence
- Pre-Beam - complete HCO, magnet ready, assembly detector ready, fiducial them, mock-up install ?, remove temporarily
- Commission - setup beam to FCUP, APERTURE, DUMP and use x-ray card to define orbit to collimator
- Experiment - install/align magnet/detector (w/ attenuators?), deliver x-rays, optimize DAQ, measure asymmetry vs. XYZ and with Wien
Older Links
- UITFList Links
- General COMTRA installation => https://tasklists.jlab.org/uitflist/tasks/107371
- DC power magnet install => https://tasklists.jlab.org/uitflist/tasks/107370
- Beamline
- Layout for RadCon media:Compton Layout for Radcon Shielding 8-10-22-3.pptx
- Spool flanges media:Flanges and Reducer for Compton and RF Kicker-jmg.xlsx
- Radiator - (1) on-hand, (1) need for BNL thumb
- Lead for UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 thumb
- Magnet
- Kepco PS - ship 8/31 2 day air => PR
- Magnet EMC PR#1PR#2 coil thumb
- Detector
- Documentation
- NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
- Manual - Sharepoint