=== New UITFList entries ===
+
== Readiness Updates ==
* General COMTRA installation => https://tasklists.jlab.org/uitflist/tasks/107371
 
* DC power magnet install => https://tasklists.jlab.org/uitflist/tasks/107370
 
  
== Readiness Updates ==
+
* Tour of installation so far [[media:220914_COMTRA.pptx]]
  
 
* ME/Layout
 
* ME/Layout
Line 15: Line 13:
  
 
* Experiment components
 
* Experiment components
** collimator installed and alignment
+
** collimator installed and aligned
 
** magnet measurement, status for install
 
** magnet measurement, status for install
 
** detector assembly, fiducialization
 
** detector assembly, fiducialization
Line 27: Line 25:
  
 
* DAQ/Controls
 
* DAQ/Controls
 +
** Helicity generator
 +
** High Voltage
 +
** EFADC/DAQ
 +
** Kepco PS
 +
 +
* Experiment sequence
 +
** Pre-Beam - complete HCO, magnet ready, assembly detector ready, fiducial them, mock-up install ?, remove temporarily
 +
** Commission - setup beam to FCUP, APERTURE, DUMP and use x-ray card to define orbit to collimator
 +
** Experiment - install/align magnet/detector (w/ attenuators?), deliver x-rays, optimize DAQ, measure asymmetry vs. XYZ and with Wien
 +
 +
 +
== Older Links==
  
 +
* UITFList Links
 +
** General COMTRA installation => https://tasklists.jlab.org/uitflist/tasks/107371
 +
** DC power magnet install => https://tasklists.jlab.org/uitflist/tasks/107370
  
===Beamline===
+
*Beamline
* Layout for RadCon [[media:Compton Layout for Radcon Shielding 8-10-22-3.pptx]]
+
** Layout for RadCon [[media:Compton Layout for Radcon Shielding 8-10-22-3.pptx]]
* Spool flanges [[media:Flanges and Reducer for Compton and RF Kicker-jmg.xlsx]]
+
** Spool flanges [[media:Flanges and Reducer for Compton and RF Kicker-jmg.xlsx]]
* Radiator - (1) on-hand, '''(1) need for BNL''' [[media:IMG_20220804_084829378.jpg|thumb]]
+
** Radiator - (1) on-hand, '''(1) need for BNL''' [[media:IMG_20220804_084829378.jpg|thumb]]
* Stands [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1 PR] [https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331093&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11 Shop Job]
+
** Lead for UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 [[media:IMG_20220804_084121573.jpg|thumb]]
* Lead for UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 [[media:IMG_20220804_084121573.jpg|thumb]]
 
  
===Magnet===
+
*Magnet
* Kepco PS - '''ship 8/31 2 day air''' => [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686 PR]
+
** Kepco PS - '''ship 8/31 2 day air''' => [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686 PR]
* Magnet [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389 EMC PR#1][https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=414754 PR#2] [[media:220810_Magnet.jpg|coil thumb]]
+
** Magnet [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389 EMC PR#1][https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=414754 PR#2] [[media:220810_Magnet.jpg|coil thumb]]
  
===Detector===
+
*Detector
* Bases - '''due 9/15 - comes with Thi in September'''
+
** Bases - '''due 9/15 - comes with Thi in September'''
* Collimator - (2) on-hand [[media:JL0015777_Cu_collimator.pdf]] [[media:IMG_20220804_082153706.jpg|thumb]]
+
** Collimator - (2) on-hand [[media:JL0015777_Cu_collimator.pdf]] [[media:IMG_20220804_082153706.jpg|thumb]]
* Absorbers - (6) on-hand [[media:Absorber - 240 D 001 14_V4.pdf]] [[media:IMG_20220804_082037794.jpg|thumb]]
+
** Absorbers - (6) on-hand [[media:Absorber - 240 D 001 14_V4.pdf]] [[media:IMG_20220804_082037794.jpg|thumb]]
* Boxes - (2) on hand  [[media:IMG_20220808_132907716.jpg|thumb]]
+
** Boxes - (2) on hand  [[media:IMG_20220808_132907716.jpg|thumb]]
* BGO - (2) on-hand [[media:IMG_20220804_084436318.jpg|thumb]] [[media:IMG_20220811_154533240.jpg|thumb]] [[media:IMG_20220811_154547652.jpg|thumb]] [[media:IMG_20220811_154606586.jpg|thumb]] [[media:IMG_20220811_154619455.jpg|thumb]]
+
** BGO - (2) on-hand [[media:IMG_20220804_084436318.jpg|thumb]] [[media:IMG_20220811_154533240.jpg|thumb]] [[media:IMG_20220811_154547652.jpg|thumb]] [[media:IMG_20220811_154606586.jpg|thumb]] [[media:IMG_20220811_154619455.jpg|thumb]]
* PMT and mu shields - (4) on-hand [[media:IMG_20220804_081738760.jpg|thumb]]
+
** PMT and mu shields - (4) on-hand [[media:IMG_20220804_081738760.jpg|thumb]]
  
===Documentation===
+
*Documentation
* NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
+
** NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
* Manual - Sharepoint
+
** Manual - Sharepoint

Latest revision as of 18:40, 14 September 2022

Thursday's @ 9am EDT by Zoom

Readiness Updates

  • ME/Layout
    • updated songsheet and quick reference, matching UED
    • dimensions when needed for S&A or Greg's Geant4 model
    • RadCon approval for lead wall, and experiment hut
  • Experiment components
    • collimator installed and aligned
    • magnet measurement, status for install
    • detector assembly, fiducialization
  • I&C jobs
    • Remote motion control for aperture (otherwise do by hand w/ access)
    • Attach current monitors to aperture and dump
    • Plumb LCW for current monitor and dump
    • Pull 6 fibers from DAQ to mezzanine
    • Align x-ray camera for x-ray card after collimator
  • DAQ/Controls
    • Helicity generator
    • High Voltage
    • EFADC/DAQ
    • Kepco PS
  • Experiment sequence
    • Pre-Beam - complete HCO, magnet ready, assembly detector ready, fiducial them, mock-up install ?, remove temporarily
    • Commission - setup beam to FCUP, APERTURE, DUMP and use x-ray card to define orbit to collimator
    • Experiment - install/align magnet/detector (w/ attenuators?), deliver x-rays, optimize DAQ, measure asymmetry vs. XYZ and with Wien