Revision as of 07:55, 22 September 2022
- Thursday's @ 9am EDT by Zoom
- Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
- Zoom ID: 160 190 6056 and Passcode: 992019
Experiment Time!!!
- UITF logbook => https://logbooks.jlab.org/book/uitflog
- UITF Compton Transmission Polarimeter Data Acquisition System
- Quick Reference v.16 media:UITF_quick_reference_rev.16.pdf
- UED List Version 4 media:comptra_beamline_v4.xlsx
- Run Plan Version 5 media:COMTRA-RunPlan-v5.xlsx
- UITF Fall 2022 Schedule
- Steps to align x-ray beam media:220920_Table_Steps.pptx
- Recent installation photos with UED names media:220914_COMTRA.pptx
Readiness Updates
- ME/Layout
- Mike/Eric completed quick reference (done, see above)
- Songsheet => use quick reference above
- Matt working with SCMB & RadCon (100 nA shielded hut, 25 nA unshielded hut)
- Experiment components
- collimator installed and aligned => see above
- magnet measurement => status...
- detector assembly, fiducialization => walkthrough completed wit
- I&C jobs
- Remote motion control for aperture (otherwise do by hand w/ access) => done
- Attach current monitors to aperture and dump => done
- Plumb LCW for current monitor and dump => done 0.75 gpm, SSG update FSD text
- Pull 6 fibers from DAQ to mezzanine (fibers arrived) => not yet
- Align x-ray camera for x-ray card after collimator => ?
- Insertable 1/2-waveplate => Shukui needs help
- pull Triax to gun rack (BCM Receiver) => done, cable #10
- DAQ/Controls
- Helicity generator
- High Voltage => tested, ready
- EFADC/DAQ
- Kepco PS
Older Links
- UITFList Links
- General COMTRA installation => https://tasklists.jlab.org/uitflist/tasks/107371
- DC power magnet install => https://tasklists.jlab.org/uitflist/tasks/107370
- Beamline
- Layout for RadCon media:Compton Layout for Radcon Shielding 8-10-22-3.pptx
- Spool flanges media:Flanges and Reducer for Compton and RF Kicker-jmg.xlsx
- Radiator - (1) on-hand, (1) need for BNL thumb
- Lead for UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 thumb
- Magnet
- Kepco PS - ship 8/31 2 day air => PR
- Magnet EMC PR#1PR#2 coil thumb
- Detector
- Documentation
- NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
- Manual - Sharepoint