Agenda:
1- Start the Readiness Review process: media:Bubble_Chamber_Readiness_11Sept2014.pdf media:Bubble_Chamber_Readiness_11Sept2014.pptx
Notes from this meeting:
- Attendees: Rossi, Freyberger, Poelker, Meekins, Grames, and Suleiman.
- Preliminary schedule of the review process:
- Bubble Chamber Safety Review: First week of December 2014 - to be able to bring the chamber on site and test it with a source.
- Experiment Readiness Review (Preliminary): First week of January 2015 - to be able to install the chamber in the injector and commission with the test beamline.
- Experiment Readiness Review: First week of May 2015 - to be able to schedule (ask for PAC days) and run the experiment at the end of Summer 2015.