#Re-measure emittance in order to analyze Run 1 conditions (3 hours) | #Re-measure emittance in order to analyze Run 1 conditions (3 hours) | ||
− | |||
− | |||
− | |||
#Test hardware TOF veto at 31MHz and 62MHz (6 hours) | #Test hardware TOF veto at 31MHz and 62MHz (6 hours) | ||
#Test FADC without TDC (2 hours) | #Test FADC without TDC (2 hours) | ||
#Test background as a function of target ladder position on large target foil (2 hours) | #Test background as a function of target ladder position on large target foil (2 hours) | ||
#Test FADC delayed operation (2 hours) | #Test FADC delayed operation (2 hours) |
Revision as of 11:22, 4 February 2015
Listed in order of suggested priority...
- Re-measure emittance in order to analyze Run 1 conditions (3 hours)
- Test hardware TOF veto at 31MHz and 62MHz (6 hours)
- Test FADC without TDC (2 hours)
- Test background as a function of target ladder position on large target foil (2 hours)
- Test FADC delayed operation (2 hours)