#Re-measure emittance in order to analyze Run 1 conditions (3 hours)
 
#Re-measure emittance in order to analyze Run 1 conditions (3 hours)
* Note laser spot sizes have been reduced by about 2
 
* Laser RF has been located closer to laser chassis
 
* Laser chassis now has internal cooling
 
 
#Test hardware TOF veto at 31MHz and 62MHz (6 hours)
 
#Test hardware TOF veto at 31MHz and 62MHz (6 hours)
 
#Test FADC without TDC (2 hours)
 
#Test FADC without TDC (2 hours)
 
#Test background as a function of target ladder position on large target foil (2 hours)
 
#Test background as a function of target ladder position on large target foil (2 hours)
 
#Test FADC delayed operation (2 hours)
 
#Test FADC delayed operation (2 hours)

Revision as of 11:22, 4 February 2015

Listed in order of suggested priority...

  1. Re-measure emittance in order to analyze Run 1 conditions (3 hours)
  2. Test hardware TOF veto at 31MHz and 62MHz (6 hours)
  3. Test FADC without TDC (2 hours)
  4. Test background as a function of target ladder position on large target foil (2 hours)
  5. Test FADC delayed operation (2 hours)