#Re-measure emittance in order to analyze Run 1 conditions (3 hours)
 
#Re-measure emittance in order to analyze Run 1 conditions (3 hours)
 
#Test hardware TOF veto at 31MHz and 62MHz (6 hours)
 
#Test hardware TOF veto at 31MHz and 62MHz (6 hours)
#Test FADC without TDC (2 hours). '''February 4, 2015:''' Added two more laser timing signals to FADC. From Disc 708, OUT signal was connected to FADC Ch10 and OUT_bar was connected to Ch12. The original laser timing signal is still connected to Ch9.
+
#Test FADC without TDC (1 hour). '''February 4, 2015:''' Added two more laser timing signals to FADC. From Disc 708, OUT signal was connected to FADC Ch10 and OUT_bar was connected to Ch12. The original laser timing signal is still connected to Ch9.
 
#Test background as a function of target ladder position on large target foil (2 hours)
 
#Test background as a function of target ladder position on large target foil (2 hours)
#Test Mott delayed operation (1 hours): a set of 10 runs while changing between No Delay and Delay=8.
+
#Test Mott delayed operation (1 hour): a set of 10 runs while changing between No Delay and Delay=8.

Revision as of 14:31, 9 February 2015

Listed in order of suggested priority...

  1. Re-measure emittance in order to analyze Run 1 conditions (3 hours)
  2. Test hardware TOF veto at 31MHz and 62MHz (6 hours)
  3. Test FADC without TDC (1 hour). February 4, 2015: Added two more laser timing signals to FADC. From Disc 708, OUT signal was connected to FADC Ch10 and OUT_bar was connected to Ch12. The original laser timing signal is still connected to Ch9.
  4. Test background as a function of target ladder position on large target foil (2 hours)
  5. Test Mott delayed operation (1 hour): a set of 10 runs while changing between No Delay and Delay=8.