Difference between revisions of "Development Period - February 9-10"
Jump to navigation
Jump to search
Line 12: | Line 12: | ||
=Test FADC without TDC (1 hour)= | =Test FADC without TDC (1 hour)= | ||
− | :* '''February 4, 2015:''' Added two more laser timing signals to FADC. From Disc 708, OUT signal was connected to FADC Ch10 and OUT_bar was connected to Ch12. The original laser timing signal is still connected to Ch9. | + | :* '''February 4, 2015:''' |
+ | ::* Added two more laser timing signals to FADC. From Disc 708, OUT signal was connected to FADC Ch10 and OUT_bar was connected to Ch12. The original laser timing signal is still connected to Ch9. | ||
=Test background as a function of target ladder position on large target foil (2 hours)= | =Test background as a function of target ladder position on large target foil (2 hours)= | ||
Line 18: | Line 19: | ||
=Test Mott delayed operation (1 hour): a set of 10 runs while changing between No Delay and Delay=8= | =Test Mott delayed operation (1 hour): a set of 10 runs while changing between No Delay and Delay=8= | ||
− | =Test new Mott DAQ Configurations (1 hour): SemiIntFast (only readout of fADC250. Blocklevel = 1) and SemiIntBlock (only readout of fADC250. Blocklevel = 50). Measure deadtime with 5 uA on 1 um gold foil. | + | =Test new Mott DAQ Configurations (1 hour)= |
+ | |||
+ | :SemiIntFast (only readout of fADC250. Blocklevel = 1) and SemiIntBlock (only readout of fADC250. Blocklevel = 50). Measure deadtime with 5 uA on 1 um gold foil. |
Revision as of 18:02, 9 February 2015
Listed in order of suggested priority...
Re-measure emittance in order to analyze Run 1 conditions (3 hours)
- February 4, 2015:
- Identified parameters and details for a procedure
- Measured emittance and Twiss for 6.3 MeV/c setup
- Started emittance and Twiss for 5.5 MeV/c but harp is stuck so test deferred for now
Test hardware TOF veto at 31MHz and 62MHz (6 hours)
Test FADC without TDC (1 hour)
- February 4, 2015:
- Added two more laser timing signals to FADC. From Disc 708, OUT signal was connected to FADC Ch10 and OUT_bar was connected to Ch12. The original laser timing signal is still connected to Ch9.
Test background as a function of target ladder position on large target foil (2 hours)
Test Mott delayed operation (1 hour): a set of 10 runs while changing between No Delay and Delay=8
Test new Mott DAQ Configurations (1 hour)
- SemiIntFast (only readout of fADC250. Blocklevel = 1) and SemiIntBlock (only readout of fADC250. Blocklevel = 50). Measure deadtime with 5 uA on 1 um gold foil.