Difference between revisions of "Bubble Chamber Meeting Wednesday July 1, 2015"

From Ciswikidb
Jump to navigation Jump to search
Line 28: Line 28:
  
 
* Cancelled shifts of beam scheduled for August except for swing shifts in second week
 
* Cancelled shifts of beam scheduled for August except for swing shifts in second week
 +
 +
* Safety Reviews:
 +
# Started pressure system approval process
 +
# Will need Electrical Review since we have 208 V custom-made electrical distribution box

Revision as of 11:51, 5 July 2015

We will meet in TL 2221 on Wednesday July 1 at 3:30 pm EST.

For those calling in we'll use the Blue Jeans [1] audio conference system.

Phone number: 1-888-240-2560
Meeting ID: 3528502673#
Meeting URL: http://bluejeans.com/3528502673


Agenda:

1- Bubble Chamber progress at Argonne




Notes from this meeting:


  • Bubble Chamber:
  1. Made the 27" stand for JLab Injector beamline
  2. Ready to start crating, expect to ship by mid-July
  3. Upon arrival at JLab, move to Injector tunnel
  4. Brad will provide description of the shipment and handling instruction
  5. Brad will be at JLab August 3 – 12.
  • Cancelled shifts of beam scheduled for August except for swing shifts in second week
  • Safety Reviews:
  1. Started pressure system approval process
  2. Will need Electrical Review since we have 208 V custom-made electrical distribution box